Technical audit of a biogas plant before purchase: a checklist for the investor
When buying an operating biogas plant, you also buy its operating history. We suggest which documents, measurements and indicators to check in the audit.
Other language versions: Polski, Deutsch, Español, Français, Italiano, Nederlands.

A technical audit before buying a biogas plant is meant to answer the question of what condition the plant is in, how much it will realistically earn and what expenses await the new owner. The seller usually shows the best year; the auditor's task is to see the whole picture. The checklist below is a starting point and should be adapted to the specific plant. The details of technical supervision inspections are covered by a separate text, and the indicators by the text on KPIs.
1. Operating documents
Ask for:
- the operator log from several years (see the text on the log),
- reports of inspections and servicing (CHP, agitators, pumps, gas system),
- the history of failures and downtime with their causes,
- operating instructions and as-built documentation,
- results of measurements and tests required in operation.
The lack of a log or gaps in it is a warning sign; the credibility of the remaining data falls.
2. Running hours and replaced components
Compare the running hours of key equipment with its expected service life and overhaul dates. For the gas engine, check how many hours have passed since the last major overhaul; the scope of overhauls is set by the manufacturer. For agitators and pumps, check the dates of replacement of bearings and seals. From these data you will calculate the upcoming overhaul expenses and enter them into the financial model.
3. Condition of tanks, membranes and sediments
The on-site assessment covers: the condition of insulation and concrete, corrosion of steel components, tightness and condition of the roof membranes, tightness of agitator penetrations. Ask when the digesters were last cleaned and how much sediment was removed; a large amount of sediment means lost usable capacity. We describe scum and sediments in a separate text. Entering a tank requires safe procedures and qualifications, so it should not be done as part of an informal inspection.
4. Process indicators from 12–24 months
Ask for monthly or weekly data: quantity and composition of feedstock, biogas production and composition, organic loading, temperature, VFA or FOS/TAC, amount of energy. Look for:
- downward trends in production per tonne of feedstock,
- seasonal process disturbances,
- dependence on a single, hard-to-obtain substrate,
- differences between declared and measured energy production.
5. Substrate stock and logistics
Check the capacity of the silage store, the stock at the end of the season, the actual supply contracts and the dependence on local suppliers. A plant with excellent parameters but dependent on a single supplier on a short contract carries a risk that is not visible in the technical documents.
6. Contracts and permits: technical scope
A technical auditor does not replace a lawyer, but should verify the conformity of the actual state with the documents: whether the installed capacity corresponds to the permits and the connection, whether the types of substrates accepted correspond to the scope of the decision, whether the technical supervision documents are up to date. Any discrepancies are passed on to the legal advisers.
7. Audit summary
The final report should contain:
- an assessment of technical condition by equipment (good, needs attention, critical),
- an estimate of overhaul expenditure for 3–5 years,
- an assessment of process stability and available reserves,
- a list of risks and missing documents,
- recommendations for negotiating the price or terms of purchase.
It is worth repeating selected measurements or inspections independently of the documents provided, especially in the area of safety.
Questions to the seller and staff
A conversation with the staff often reveals more than the documents. Ask what breaks most often, which alarms appear most often, what a typical winter and summer look like in operation, what changes have been made to substrates and which work is being put off. Ask also who operates the plant, how many people know the system and whether there is a procedure for cover. Compare the answers with the documents: discrepancies are information. It is also good practice to see the plant at different times of day and during normal operation, not only during a prepared visit.
Practical notes
When planning the audit, reserve several days on site and access to the data in advance, so that the trend analysis is not done in a hurry. If possible, compare the plant with others of similar size and substrate profile, taking care in interpretation, because conditions differ. Hand over the audit results in a form that allows later updating, for example as a list of risks with a severity rating and an estimate of the cost of remedying them.
What the audit does not settle
A technical audit does not value the plant or assess its profitability in isolation from energy prices, contracts and financing conditions. It does, however, supply input figures for such a valuation: expected overhaul expenditure, real availability and process stability. That is why the audit results should go at the same time to the financial and legal adviser. It is worth agreeing the report format with them in advance, so that technical risks can be translated into provisions of the purchase agreement, for example a price adjustment or a seller's guarantee on specified equipment. In case of doubt about the assessment of the condition of a specific device, an independent inspection by the manufacturer or a specialised service provider should be commissioned.
What to remember
- You are buying an operating history, not only equipment.
- Documents and indicators from 1–2 years say more than a single good month.
- Include overhaul expenditure in the price.
- The technical, legal and financial scope of the audit must be separated and coordinated.