Biogas plant downtime cost: how to calculate lost output, penalties and hidden costs
The cost of downtime is more than lost energy: fixed costs, risk to the biology and substrate storage are added. A model with parameters to plug in.
Other language versions: Polski, Deutsch, Español, Français, Italiano, Nederlands.

The cost of biogas plant downtime is not only the energy that was not sold, but the sum of effects, some of which become visible only after weeks. A good model makes it possible to compare the cost of an hour of downtime with the cost of a parts stock, faster servicing or insurance. Below we give the structure of the calculation with parameters to plug in; all numbers are illustrative and hypothetical, and market prices are not given as fact. The structure of annual costs is covered by the text on OPEX, and the availability methodology by the text on MTBF and MTTR.
Basic calculation
Direct loss per day:
S = E × c − K_z
where E is the energy lost during the day (kWh), c is the unit revenue (PLN/kWh, including all components, for example energy, heat, any support), and K_z is the variable costs that the downtime avoided, for example part of the dosed substrates, oil consumption, transport costs.
A hypothetical example: an engine with an electrical output of 500 kW generates about 12,000 kWh per day. At a unit revenue of PLN 0.60/kWh (an example value) this gives PLN 7,200. If the variable costs saved are PLN 1,500, the daily loss is PLN 5,700.
Fixed costs
Loan instalments, wages, insurance, lease, fixed charges: all of these run regardless of operation. Do not subtract them from the loss. If the company had no downtime, it would earn revenue covering these costs; downtime takes away the revenue, and the costs remain.
Hidden costs
- Risk of losing the biology. A longer shutdown and process upsets may require a slower return to full load. The losses then continue not only during the failure itself.
- Substrate storage. Deliveries that cannot be accepted require space, protection, and sometimes disposal; silage on the clamp keeps ageing.
- Contractual penalties and loss of offtake. Contracts for the supply of energy, heat or gas may have minimum delivery conditions. Check them in your documents.
- Urgent repair costs. Express transport, overtime work and weekend service usually cost more.
- Reduced output after return. Restart requires the time described in the guide on the maintenance shutdown.
Parameters to plug in
Build a spreadsheet with fields: power and daily yield, unit revenue, avoided variable costs, number of days of downtime, number of days of reduced output after the return and the percentage of reduction, storage costs, penalties, costs of urgent service. This lets you simulate scenarios: a failure lasting three days, a week, a month.
Differences depending on the route
In a cogeneration plant the loss concerns the sale of electricity and heat. A lack of heat offtake may additionally limit engine operation. In a biomethane plant, a stoppage of the upgrading unit usually means that raw gas has to be burned in a flare or stored, and revenue from biomethane sales falls, while process costs keep running. There are also obligations resulting from the connection agreement and supply contracts, whose terms are individual.
Loss-of-profit insurance
A policy covering business interruption after machinery breakdown (in general) usually has a time excess, that is a number of days for which no compensation is due. This means that short downtimes are most often covered by you yourself. Conditions, exclusions and limits must be checked in the offer; they cannot be generalised. Comparing the premium with the value of the risk requires your own downtime model.
How to use the result
Multiply the daily loss by the number of days of expected downtime in a year, estimated from historical data. You will obtain an approximate annual value of the risk, which you can compare with the cost of countermeasures: a parts stock, a service agreement, an additional sensor, staff training.
Example with hidden costs (hypothetical)
For example: the downtime lasts 5 days, the daily loss is PLN 5,700, that is PLN 28,500. To this we add two days of reduced output after restart with a drop of 30% (about 2 × 0.3 × PLN 7,200 = PLN 4,320), urgent weekend service (PLN 3,000) and additional substrate storage (PLN 2,000). In total this comes to about PLN 37,800, that is almost a third more than the direct loss alone. All values are examples; the point is to show that omitting hidden components systematically understates the result and leads to underestimating the profitability of a parts stock or faster servicing.
How this calculation supports decisions
A downtime cost calculation makes sense only when it feeds into specific decisions: whether to buy a stock of class A parts, whether to sign a service agreement with a guaranteed response time, whether to install a second sensor at a critical point. For each of these options, compare the annual cost of the measure with the product of the probability of failure, the expected downtime and the daily loss. If the cost of the measure is clearly lower than the expected loss, the decision is easy. When the two are close, the result is decided by factors that are harder to measure, such as the risk to the biology of the process or obligations to buyers. The model is worth updating once a year, after the annual operational review, because prices, plant load and failure history change. The same approach can be used to compare different scenarios, for example a short but frequent interruption with a rare but long one.
What to remember
- Loss = lost revenue minus avoided variable costs; fixed costs remain.
- Hidden components can be as large as the direct ones.
- Build the model on your own numbers, not other people's prices.
- The result serves to compare investments in reliability.