Cogeneration and enginesAnalysis
One large unit or two smaller ones: redundancy, efficiency and cost at a biogas plant
A comparison of 1×1 MW and 2×500 kW configurations in an illustrative example: availability, part load, costs, heat and a lost production model.
Other language versions: Polski, Deutsch, Español, Français, Italiano, Nederlands.

When designing or expanding a biogas plant the question arises whether to obtain the electrical capacity, for example 1 MW, from one unit or from two of 500 kW each. Two smaller units give greater availability and flexibility; one large unit is usually cheaper per kilowatt and somewhat more efficient. The right choice depends on the cost of downtime, the gas profile and heat offtake. This article compares the two configurations in an illustrative example. All the figures are working assumptions, not data from a specific installation.
Availability and downtime
A CHP unit has planned downtime for inspections (oil and spark plug changes, valve inspections, major overhaul) and unplanned failures. The typical availability of a well-serviced unit is, indicatively, in the range of 92–97% of the year. With one large unit every outage means a complete absence of electricity and heat production, unless there is a standby boiler. With two units the outages do not overlap (with good planning), so during that time half the capacity operates.
A simple lost production model
Assumptions: total capacity 1,000 kW, revenue from the sale of energy and heat equal to PLN 0.40/kWh, availability of each unit 95% (downtime 5% of the time, that is about 438 hours a year). Operation at full load.
- The 1×1000 kW option. Lost production is 438 h × 1,000 kW = 438,000 kWh, that is about PLN 175 thousand a year.
- The 2×500 kW option. Lost production of each unit is 438 h × 500 kW = 219,000 kWh. The outages are spread over time and do not overlap, so the total loss is likewise 438,000 kWh. The difference appears only when we distinguish longer failures: with a large unit a 30-day outage takes away all the revenue, and with smaller ones only half, which matters for liquidity and contractual penalties.
The average loss is therefore similar, but the risk is distributed differently. The greatest gain from two units appears when a failure requires a long wait for a part or an off-site overhaul, and the gas can then be processed by the second unit instead of being burned in the flare. Unused gas is lost energy, and where gas storage is limited it also means a risk of emissions or the need to curtail feeding of the digesters.
Part load and efficiency
A large engine has a higher electrical efficiency (of the order of 42–44% for units in the 1 MW class) than a smaller one (of the order of 39–42% for 500 kW), indicatively by 1–3 percentage points. For the same amount of gas that is about 2.5–7% more electricity. On the other hand, when gas production is variable, one large engine often runs at 60–70% load, where efficiency falls by a few points, whereas of two engines one can run at full load and the other tops up. The rule: the greater the variability of the gas, the more advantages splitting the capacity has.
Costs
| Item | 1×1000 kW | 2×500 kW |
|---|---|---|
| Investment cost per kW | lower, indicatively by 5–15% | higher: two sets of equipment, switchgear, two chambers |
| Annual service per kWh | lower thanks to scale | somewhat higher; more visits, but smaller parts |
| Major overhaul | one larger sum | two smaller ones, spread over time |
| Space and containers | one container or hall | larger area |
| Grid connection | one transformer | often one shared, or possibly two |
The differences in cost should be checked in offers, because they depend on the manufacturer and market conditions.
Heat and logistics
Two units make it possible to match heat production better to the season: in summer one runs, in winter both. In the option with one large unit the seasonality of heat offtake forces operation at part load or the use of dump cooling. With two units the service technician can replace parts in one without stopping the plant, which makes it easier to plan inspections, and the parts store is shared if the same model has been chosen.
When to choose which option
- One large unit is chosen when the gas is stable and highly predictable, the heat consumer is constant and a standby boiler or fast service is available.
- Two smaller units are better with variable gas production, with plans for phased expansion, with seasonal heat offtake and where downtime is very costly (contractual penalties).
- An intermediate solution is a main unit of larger capacity and a small unit to cover peaks and winter operation.
The final choice is worth basing on a calculation with your own data: availability from the service documentation, the gas profile from process data and the heat offtake plan. The efficiency at part load, which affects this calculation, is described in the article The CHP engine at a biogas plant: electrical and thermal efficiency and part-load operation.