Safety and ATEXGuide

Subcontractors and contracted work at a biogas plant: OHS coordination and cooperation between employers

Servicing and repairs at a biogas plant are often carried out by outside people. How to organise employer cooperation, a coordinator, permits and acceptance of work.

Published 5 min readFeedstockData Editorial Team

Other language versions: Polski, Deutsch, Español, Français, Italiano, Nederlands.

Pusta, nowoczesna sala posiedzeń rządowych z długim stołem, teczkami i raportami oraz widokiem na miasto przez duże okna.
Illustration: FeedstockData (AI, Google Gemini)

At a biogas plant most of the riskiest jobs – engine servicing, tank cleaning, agitator repair, automation inspections – are done by people from outside the plant, who do not know its dangerous places. The safety of such work is not only their concern: the installation is the workplace of the client, and the client is responsible for part of the hazards.

The basis: Article 208 of the Labour Code

Article 208 of the Polish Labour Code concerns the situation when employees of several employers work in the same area. It requires employers to cooperate, to appoint a coordinator supervising the occupational health and safety of all persons in that area, to agree cooperation rules covering how to act in the event of hazards, and to inform each other about hazards. For the exact wording and further obligations, consult the current text of the Act. Additional obligations follow from the regulations on OHS during construction works and from the explosion protection document, which also takes contractors' work into account.

The coordinator

The coordinator is appointed by name, preferably from among people who know the site – usually the manager or operator. Their tasks: giving the contractor information on hazards, agreeing the scope and dates of work, ensuring permits are in place, supervising compliance with the rules and the right to stop work. The coordinator must have real authority and time; appointing a person "on paper" who is not present at the site does not meet the purpose of the regulation.

Information on hazards

The contractor must be given knowledge they do not have:

  • the H2S hazard: where it may occur (around the digester, the digestate tank, the gas system, manholes), what the alarms and escape routes are;
  • explosion hazard zones: a plan with the zones marked, rules for using tools and electrical equipment, phones and vehicles;
  • confined spaces: a ban on entry without a permit, and the procedures;
  • energy and utilities: places to isolate power, gas and pressure, the lock-out and tagging procedure (LOTO);
  • vehicle movements: routes of loaders and tankers, speed, pedestrian zones;
  • alarm signals, assembly point, emergency numbers, location of the first aid kit and defibrillator.

The information is given in writing and acknowledged by signature; an oral "be careful over there" is not enough.

Requirements for the contractor

Before signing a contract or admitting to work, it is worth verifying: valid medical examinations and OHS training of employees, qualifications for the type of work (electrical, welding, work at height, machine operation), liability insurance, knowledge of the requirements for Ex zones (training, antistatic clothing, non-sparking tools where indicated), personal protective and detection equipment. The contract can set out rules: the right to stop work, the duty to report incidents and a ban on entrusting work to lower-tier subcontractors without the client's consent.

Entry briefing and permits

Every new contractor employee should go through a short briefing before first entry: rules of movement, hazards, prohibitions (smoking, equipment that may spark), alarm signals, how to report accidents. For higher-risk work, such as hot work, entry into a confined space, work at height, work on a live electrical installation or gas isolation, a written permit is issued stating the scope, hazards, measures, validity period and responsible persons. The permit expires at the end of the shift or on a change of conditions.

A model entry card for contractors

The entry card may contain the following fields:

  1. contractor company and contact person;
  2. scope, place and date of work;
  3. list of persons with confirmation of training, medical examinations and qualifications;
  4. confirmation of the briefing (date, signature, person conducting it);
  5. hazards identified by the client and by the contractor;
  6. required measures: permits, energy isolation, detection, PPE;
  7. coordinator on the client's side and supervisor on the contractor's side;
  8. list of equipment brought onto the site;
  9. procedure in case of an alarm;
  10. completion record: condition of the workplace, acceptance, comments.

Supervision and acceptance of work

The coordinator visits the workplace during the work, especially during hazardous tasks. After completion, the client checks whether the safeguards have returned to working condition: valves in the working position, switches restored, disconnected supplies operational again, sensors and alarms with no bypasses, tools removed, guards fitted. In many incidents the cause was that a safeguard was not restored after servicing, not the servicing itself.

Example: replacing an agitator in a tank

The client wants to replace the agitator in a digester, and the work will be done by an external company together with a crane company. So three entities work in one area: the plant, the service contractor and the crane operator. A sensible sequence looks like this: 1) before entry the client gives all contractors written information on hazards (H2S, the Ex zone around the digester, confined space, vehicle movements); 2) the appointed coordinator sets the order of work and the places where work cannot be done simultaneously; 3) before starting, permits for hazardous work are issued, valid only for the specific shift; 4) after completion the coordinator, together with the contractor's manager, checks whether the safeguards have returned to working condition.

It is worth recording who is responsible on a given day for shutting down the installation and securing it against accidental start-up. Unclarity over whether the lock is applied by the client or the contractor is sometimes the cause of dangerous situations. The rules of energy isolation are described in the article on machine safety and LOTO, and the classification of places around the digester in the article on explosion hazard zones.

Typical mistakes

  • A contractor starts work "on a password" without initial training.
  • No coordinator, or an absent coordinator.
  • A permit issued in advance for many days.
  • No acceptance after completion and no restoration of safeguards.
  • Sharing documents without passing on information about Ex hazards.