Cogeneration and enginesGuide

Transformer and MV switchgear at a CHP plant: sizing, losses, earthing and inspections

The unit transformer and MV switchgear connect the CHP unit to the grid. We explain sizing with cos φ, the cost of losses, neutral earthing and the scope of inspections.

Published 4 min readFeedstockData Editorial Team

Other language versions: Polski, Deutsch, Español, Français, Italiano, Nederlands.

Dłonie dwóch osób nad rysunkami technicznymi biogazowni na stole, pióro i kawa w ciepłym świetle.
Illustration: FeedstockData (AI, Google Gemini)

The unit transformer raises the generator voltage (typically 0.4 kV) to the level of the MV network (for example 15 or 20 kV), and the MV switchgear enables switching, protection and metering. Their selection affects the investment cost, the annual losses and the reliability of the whole biogas plant. All parameters in the text are indicative; the final values are determined by the designer and the DSO.

Sizing the transformer

Apparent power of the generator: S = P / cos φ. For a CHP unit of 500 kW electrical at cos φ = 0.8 the apparent power comes to 625 kVA, and at cos φ = 1 it is 500 kVA. The transformer is chosen so that it carries the apparent power of the generator, reduced by the supply of auxiliary loads if these are connected behind the transformer, with a margin in the order of 10–20% for voltage deviations and expansion. The nearest standard rating is, for example, 630 kVA. A transformer that is too large increases no-load losses and cost, and one that is too small risks overload and overheating, especially in summer.

It is also worth checking:

  • The vector group (for example Dyn11) consistent with the DSO requirements and with the earthing on the low-voltage side;
  • The short-circuit voltage (impedance), which affects the short-circuit current and the voltage drop under load;
  • The tap changer range (usually ±2 × 2.5% off-load), to match the voltage to the grid conditions.

Losses as an annual cost

No-load losses P0 occur whenever the transformer is energised, regardless of load. Load losses Pk grow with the square of the current: Pk(load) = Pk · (S/Sn)². Ecodesign requirements limit the losses of new transformers, and the market offers units with reduced losses.

Illustrative example. A 630 kVA transformer: no-load losses 0.8 kW, load losses 6.5 kW at rated output (hypothetical values). Operation of 8000 h/year at 80% load:

  • no-load: 0.8 kW × 8760 h ≈ 7000 kWh,
  • load: 6.5 × 0.8² × 8000 ≈ 33,300 kWh,
  • in total about 40 MWh/year; at an energy price of PLN 450/MWh that is about PLN 18 thousand per year.

A difference in losses of a dozen or so percent between units over 25 years gives an amount that justifies a surcharge for a transformer with lower losses. For a used transformer with unknown losses, the analysis must be carried out on the basis of the rating plate.

Neutral point earthing

An MV network can have an isolated neutral, a neutral earthed through a resistor or through an arc suppression coil. The method of earthing is determined by the DSO and affects the earth-fault protection of the generator and the transformer. On the low-voltage side of the transformer a network system (TN, IT) is used in accordance with the design. Earthing requires careful execution and periodic resistance measurements, and at a biogas plant also potential equalisation with the explosion hazard zones.

MV switchgear

A typical switchgear contains a transformer or line panel with a circuit breaker or a switch-disconnector with fuses, a generator panel, metering and protection. The important parameters are the rated current, the short-circuit withstand (kA for 1 s), the internal arc resistance and the loss of service continuity class. Circuit breakers and relays require periodic inspections of the operating mechanism, lubrication, checking of the contacts and tests of the interlocks.

Inspections and tests

  • Transformer: checking the oil level and tightness (if oil-filled), temperature, dissolved gas chromatographic analysis for larger units, testing of insulation resistance and ratio, condition of the breather, cleanliness of the insulators.
  • MV switchgear: mechanical inspection, testing of the circuit breakers, checking of the settings, thermography under load.
  • Earthing and protection against electric shock: measurements of earthing resistance, of the effectiveness of automatic disconnection or shock protection, and of the continuity of protective conductors; the intervals result from regulations and recommendations, usually every few years, and thermography annually.
  • Other: transformer oil, fire protection, oil containment tray.

Work safety

Work on MV equipment is carried out only by qualified persons, according to operating instructions and work organisation (isolation, securing against reconnection, verification of the absence of voltage, earthing, marking of the work area). With two sources of supply, that is the grid and the generator, the possibility of back-feed voltage must be kept in mind.

Day-to-day operational checks

The operator can personally check the items that do not require authorisation for live work: sounds and smell, temperatures from the indicators, oil level, tightness, the condition of the oil containment tray and the surroundings of the transformer (vegetation, foreign objects). Unusual humming, a rise in temperature or a leak is reported to an authorised person. The schedule should also include thermography of the terminals under load, because loose connections show up as a rise in temperature long before a failure.

Summary

The transformer and the switchgear are unglamorous, but the failure of either one stops the whole plant. The balance of production, own consumption and energy sales is described in the article Electricity balance of a biogas plant. Size the rating from the apparent power, calculate the losses over the life of the facility, agree the earthing with the DSO and plan the tests into the inspection schedule.

Sources

  1. Dyrektywa 2014/35/UE (LVD) w sprawie sprzętu elektrycznego
  2. Rozporządzenie Komisji (UE) 548/2014 w sprawie ekoprojektu dla transformatorów
  3. Polski Komitet Normalizacyjny — katalog norm PN-EN (transformatory, rozdzielnice)