Safety and ATEXGuide
Hot work at a biogas plant: permit, welding and cutting, gas checks and fire watch after the work
Welding, cutting and grinding near a biogas installation require a written permit, gas measurements and a fire watch. We describe the procedure step by step.
Other language versions: Polski, Deutsch, Español, Français, Italiano, Nederlands.

Hot work is one of the most common causes of ignition in installations with flammable gas. Welding a pipe, cutting with a grinder or drilling in an enclosure produce sparks and hot metal, which can ignite gas, dust or combustible materials in the surroundings. Effective protection rests on three elements: a written permit with clear conditions, gas measurements and a fire watch after the work is finished. Below we discuss the procedure and typical pitfalls at a biogas plant. Fires and their causes are described in the article Fires at biogas plants, and the requirements for the explosion protection document in the text ATEX at a biogas plant: directives, obligations and the explosion protection document.
What counts as hot work
Hot work includes everything that can produce an ignition source:
- gas or electric welding and cutting,
- grinding, disc cutting and mechanical brushing, which generate sparks,
- soldering and the use of torches and heat guns,
- drilling and driving into steel structures in hazardous zones.
Even seemingly safe equipment, such as a drill without Ex certification, is an ignition source in a zone. That is why the rule "just for a moment" does not apply.
Hot work permit
The permit is a written document issued before the work starts. It should contain:
- a description of the work and the location, and the persons carrying it out,
- the person issuing the permit and the person responsible for carrying out the work,
- the appointment of a fire watch for the duration of the work and after it,
- the result of flammable gas and oxygen measurement before starting,
- protective measures: isolation of the installation, shields, fire extinguishers,
- the period of validity and the conditions for stopping the work,
- signatures closing the permit after the area has been checked.
The permit also covers subcontractors who do not know the installation. Before the work they must be briefed on the hazards and on prohibited places.
Preparing the installation and gas measurement
At the work site, combustible materials are removed or protected with non-combustible shields (welding blankets). The installation concerned is isolated from gas flow by blanks or flanges with isolation equipment, not by a valve alone. The pipeline or tank is cleared of residual gas by purging or inerting (in line with the start-up and shutdown procedure).
Gas is measured:
- before the work starts, at several points, including in depressions and ducts,
- during the work, continuously or at set intervals, depending on the risk assessment,
- after every break longer than that specified in the procedure.
A result above the agreed threshold, usually a small fraction of the LEL, means the work is stopped. The measurement is taken by a trained person, with a meter with current calibration and approval for use in the zone.
Flammable parts of the installation
At a biogas plant many parts are flammable or easily ignited, and their condition is not always visible: tank membranes and films, thermal insulation made of foams and wool with a flammable facing, gaskets, electrical cables, deposits and dust on structures. A spark from a grinder can travel more than a dozen metres and ignite a film or insulation. For this reason hot work is not carried out on gas covers or on tank roofs; if it is unavoidable, it requires complete emptying and removal of gas, a separate assessment and the consent of the responsible person.
Drilling and grinding
A common mistake is to regard drilling and grinding as less dangerous than welding. Both activities generate mechanical sparks and hot swarf. In hazardous zones, tools in Ex design or with limited sparking are permitted, or "cold" work is carried out (for example cutting with a pneumatic saw), if it has been assessed. The use of unapproved tools requires a permit that excludes an explosive atmosphere during the work.
Fire watch after completion
After the ignition source has been extinguished, insulation may still smoulder or metal may still glow. The fire watch remains on site after the work, usually at least 1–2 hours; in places with combustible insulation or hidden spaces the time can be longer. After this time, a round with inspection is carried out, including adjacent spaces, using a thermal imaging camera if available. Only then is the closing of the permit signed.
Example of work organisation
Replacing a section of pipeline at the blower might look like this: stopping the blower and engine, blanking the pipeline on both sides, purging with nitrogen with methane monitoring, marking out the area with tape and fire extinguishers, gas measurement before the first cut and every dozen or so minutes during the work, and after completion a round with the fire watch and only then unlocking the installation. The whole takes more time than the welding itself, but it is precisely this time that distinguishes planned work from risky work. If any condition of the permit ceases to be met, for example the wind changes direction or the meter shows a rise in gas, the work is stopped immediately, and resumption requires a new measurement and confirmation.
Typical mistakes
- A permit "for everything" with no description of the place and conditions.
- No fire watch, or a fire watch busy with another task.
- A valve instead of a blank as the only isolation of the installation.
- Gas measured only once, at the start of the shift.
- Work on or above a gas cover.
- Ending the watch at the moment the equipment is switched off.