Tanks and membranesGuide
Water tightness test of a tank before start-up: procedure, criteria and documentation
Before substrate enters the tank, it is checked with water. We describe the stages of the test, the correction for evaporation and temperature, the observation of damp patches and the acceptance record.
Other language versions: Polski, Deutsch, Español, Français, Italiano, Nederlands.

A water tightness test is the cheapest way to detect tank defects before substrate is introduced. The tank is filled with clean water to the working level and its behaviour is observed for a specified time. Only a positive result entitles one to proceed to further stages, such as insulation, backfilling and start-up. It is supplemented by a tightness test of the cover and the gas system, which is carried out later, on inert gas or air.
Preconditions
Before the test starts, the following conditions should be met:
- the concrete has reached the strength and age required in the specification,
- all process penetrations and seals are installed,
- the outer surfaces are still accessible (not insulated and not backfilled),
- a source of water is provided in a quantity corresponding to the volume of the tank, as well as a place to dispose of it after the test,
- level gauges or level sensors of known accuracy have been prepared, together with a thermometer for measuring water and air temperature.
The water after the test can often be used for start-up as a dilution medium, if it is clean and at the right temperature.
It is also worth determining in advance who is responsible for the individual tasks: filling, level readings, the walk around the perimeter and keeping the record. Readings taken by one designated person at a fixed time are more comparable than notes collected at random by several people. Before the test starts, check that the valves are closed and the ports are blanked off, because an open or leaking connection can falsify the whole measurement.
Filling stages
Filling is divided into several steps, for example every one third of the height. After each stage the inflow is stopped for a few hours and the wall and floor are inspected. Staging makes it possible to detect a leak at a low level, when it is small and easier to repair, and the structure is not yet fully loaded. During filling, any settlement of the slab is also observed, measured at points on the perimeter.
Stabilisation period and measurement
After the working level is reached, there is a stabilisation period in which the concrete saturates with water and minor external damp patches may gradually disappear. Only then does the actual measurement begin. It typically lasts from several to over ten days, but the length and the permissible drop are determined by the design or the specification. The level is read at fixed times, and alongside it the water and air temperature, precipitation and sunshine are recorded.
Correction for evaporation and temperature
The drop in level has several causes: a possible leak, evaporation from the water surface and changes in water volume due to temperature. To separate them from a leak, a reference vessel is used (for example an open container of water with the same exposure), which measures evaporation alone. The difference between the drop in level in the tank and in the vessel gives an estimate of the real loss. A hypothetical example: with a water surface of 400 m², a drop of 1 mm is 0.4 m³ of water; if the reference vessel showed 3 mm of evaporation and the tank 4 mm, the excess of 1 mm corresponds to about 0.4 m³ of possible loss in the given period.
Observation of damp patches
Independently of the level measurement, one walks around the perimeter, noting damp patches, efflorescence and drops. Special attention is paid to the joint between the wall and the slab, construction joints, pipe penetrations and cracks. Damp patches are photographed and marked on a drawing with the date. After the level is lowered, patches that have disappeared indicate saturation of the concrete rather than a leak.
What to do in case of a leak
If the result does not meet the criterion or leaks are visible:
- Locate the spot: lower the level to the height at which the leak stops.
- Assess the cause (crack, construction joint, penetration seal).
- Plan the repair using a method consistent with the principles of PN-EN 1504 – injection, sealing, gasket replacement.
- After curing and waiting for the required time, repeat the test.
Allowing start-up without repeating the test means a risk of a leak in a tank that already contains substrate.
Record and link with acceptance
The record contains: the date and time of the start, the initial and final levels, temperatures, data from the reference vessel, the result of the damp patch observation, the acceptance criterion and the signatures of the client, the contractor and the inspector. It is one of the final acceptance documents and a point of reference in warranty disputes. After the test, the tank is emptied or conditioned for start-up; the process is described in the article Digester start-up step by step.
What to look out for
Plan the water logistics and its disposal in advance as well. A large tank requires thousands of cubic metres, so the intake, permits and discharge location must be known before filling starts. In winter, water freezing and pipe protection must also be taken into account, and the test should be carried out in a weather window that does not force haste.
Summary
The water test is simple but requires discipline: staged filling, stabilisation, correction for evaporation and a reliable record. Skipping or shortening it costs far more later than a few days of waiting.