CHP service contract: full service or time and materials — scope, KPIs and penalties
Full service, time and materials or a hybrid model. We compare the scope, availability, response times and clauses that often work against the owner.
Other language versions: Polski, Deutsch, Español, Français, Italiano, Nederlands.

Choosing the model of a service contract for a CHP unit is a choice between a fixed price with a transfer of risk (full service) and paying for the actual scope of work (time and materials). Neither model is universally better. The decision depends on the age of the unit, the operating hours, the experience of the operating staff and the owner's willingness to bear risk. The article is a summary of practical issues, not legal advice.
Contract models
| Model | How you pay | Advantages | Disadvantages |
|---|---|---|---|
| Full service | a fixed rate per operating hour or per MWh (for example a dozen to several dozen PLN/MWh, depending on the engine) | predictable cost, overhaul risk on the contractor's side | higher price, exclusions, little control over the scope |
| Time and materials | an hourly rate and part prices | you pay for the work actually done, the possibility of choosing the contractor | risk of large emergency costs, no guarantee of availability |
| Hybrid | routine inspections as a lump sum, overhauls separately or with a cap | a compromise | requires precise definitions |
The price range in the table is only a rough indication and depends on output, manufacturer, age and region. It should always be verified in the offer.
What is usually included and what is not
Elements to be clearly agreed:
- Consumables: oil, filters, spark plugs, gaskets; whether they are included in the rate or charged separately.
- Major overhaul (replacement of the crankshaft, pistons, liners, cylinder heads) after a defined number of operating hours; whether it is included in the rate.
- Additional equipment: coolers, exhaust heat exchangers, catalyst, gas systems, controls and the generator; often partly outside the scope.
- Travel and standby, work at night and on holidays, waiting time.
- Failures caused by the operator (poor gas quality, missed inspections) are usually excluded.
- Failures caused by gas parameters, for example siloxanes or H2S above the limits given by the manufacturer.
Guaranteed availability
Availability is most often calculated as the ratio of readiness hours to calendar hours in the settlement period. Agree: whether the time of planned inspections is excluded, whether failures from external causes (grid outage, lack of gas) are excluded, how downtime is measured (from the report, from the stop) and who carries out the measurement. Guarantees at the level of 95–98% are encountered, but with a poorly defined indicator they give no real protection. The exact definition is more important than the number itself.
KPIs, response times and penalties
- Response time: by telephone (for example within several hours) and on site (for example within a day), separately on working days and on holidays.
- Repair time: targets for typical faults; for a major overhaul a schedule.
- Availability of parts: a list of critical parts in a local warehouse or the delivery time.
- Contractual penalties: for exceeding the repair time or lower availability, preferably proportional to the lost revenue; there is often a limit of liability, for example up to the amount of the annual fee.
- Bonuses: for achieving higher availability may motivate the contractor.
Clause pitfalls
- General exclusions ("improper operation") without a definition.
- A unilateral change of rates or indexation without an upper limit.
- A change of inspection intervals on the contractor's side, which lengthens downtime.
- No access to diagnostic data and software, which creates dependence on a single service provider.
- A restriction on the right to commission auxiliary work from other companies without losing the warranty.
- No provisions on the technical condition of the engine at the end of the contract.
Assignment, end of contract and data
Check whether the contract can pass to a new owner of the installation, whether it provides for a notice period and possible penalties for early termination. At the end it is worth having the right to a technical condition report, the documentation of the work and the service data, and a handover protocol. This way the next contractor does not start from zero.
How to compare offers
When comparing offers, convert each into PLN/MWh for several production scenarios (for example 6500, 7500 and 8200 operating hours per year) and for one scenario with a major failure. Add the costs left out of the rate: oil, travel, additional equipment and possible penalties for exceedances. Ask for references on the availability actually achieved on similar units, and not only the guaranteed one. A transparent offer shows what is in the price and what is not. The scope of typical service work (oil, spark plugs, overhauls) is described in the article Servicing gas engines in CHP units, and the criteria for a decision on a major overhaul in Major overhaul or replacement of a CHP unit. The cost of downtime, which is worth knowing before negotiating contractual penalties, is shown in the article The cost of biogas plant downtime.
Summary
For new units within the warranty period, full service or a hybrid with a clear scope is advantageous. For older units, a time and materials model with a cost cap or a risk-sharing rule is reasonable. Before you sign, calculate the total cost per MWh from different scenarios and consult the contract with a lawyer.