Are slurry and manure UPPZ?

Yes. Manure, unmineralised guano and digestive tract content are Category 2 material (Article 9(a)). In a biogas plant, however, they can be processed without prior sterilisation if the competent authority sees no risk of the spread of a serious transmissible disease.

Sources: Rozporządzenie (WE) nr 1069/2009 — uboczne produkty pochodzenia zwierzęcego (EUR-Lex); Rozporządzenie Komisji (UE) nr 142/2011 — przepisy wykonawcze (EUR-Lex)

Discussed in the article: UPPZ: Regulation 1069/2009 and material categories 1, 2 and 3 in a biogas plant

Link to this answer

Are there regulations on odour nuisance from biogas plants in Poland?

The regulations on odours in Poland are general in nature: odour nuisance is assessed on the basis of the Environmental Protection Law, environmental decisions and permits, and there is no separate, detailed odour act (as of October 2026: no such act in the ELI database of the Journal of Laws).

Authorities may impose requirements in decisions, e.g. concerning covered storage, filters, the method of unloading substrates and the use of digestate, and residents may submit complaints to the village head or mayor and to the environmental protection inspectorate. Sources of odour are not only digesters but also the unloading of waste, silage stores and the spreading of digestate on fields. Good practices (enclosing facilities, short storage time, injection or rapid incorporation into soil) limit the nuisance. Check whether the regulations have changed since our write-up. This is general information.

Sources: Ustawa Prawo ochrony środowiska — ISAP; Główny Inspektorat Ochrony Środowiska — gov.pl

Link to this answer

Are these the final rates?
Can a 1 MW Lithuanian biogas plant get a feed-in tariff?

Not in the model described in the EurObserv'ER overview: the feed-in tariff is available to installations of up to 10 kW. A biogas plant larger than 10 kW can obtain a market premium only by taking part in an auction.

Sources: EurObserv'ER — Renewable energy policy factsheet 2020: Lithuania; VERT — aukcje energii odnawialnej; TaiyangNews — Bidders seek €0/MWh market premium in Lithuania auction

Discussed in the article: Lithuania: how energy from biogas is supported — a tariff for small installations, premium auctions for the rest

Link to this answer

Can a biogas plant accept animal by-products?

Yes, but only once the requirements of Regulations (EC) No 1069/2009 and (EU) No 142/2011 are met: the installation must be approved, and Category 3 material undergoes hygienisation, usually 70 °C for 60 minutes with particle size reduced to 12 mm.

Animal by-products are divided into three risk categories. Category 3 material (e.g. slaughter waste fit for human consumption) can be processed in a biogas plant after hygienisation. Category 2 material usually requires pressure sterilisation or is permitted in strictly defined cases (e.g. manure, digestive tract content). Category 1 material is excluded from digestion in a typical biogas plant. Supervision is exercised by the Veterinary Inspectorate, which approves establishments. Remember that digestate from such materials is subject to separate rules on application. This is general information.

Sources: Rozporządzenie (WE) nr 1069/2009 (uboczne produkty zwierzęce) — EUR-Lex; Rozporządzenie (UE) nr 142/2011 (uboczne produkty zwierzęce — przepisy wykonawcze) — EUR-Lex

Link to this answer

Can a biogas plant agree to power curtailment in exchange for faster connection?

Yes. For installations with a biogas store, the application may include a declaration of unconditional power curtailment at set times of the day and year, and the agreement must guarantee the ability to deliver power for at least 12 hours a day without compensation.

Sources: Ustawa z 10 kwietnia 1997 r. – Prawo energetyczne (art. 7) — Internetowy System Aktów Prawnych; Urząd Regulacji Energetyki

Discussed in the article: Connecting a biogas plant to the electricity grid: conditions, advance payment, contract, stages

Link to this answer

Can a biogas plant be built near a Natura 2000 area?

It can, but in the environmental procedure the impact of the investment on protected areas is assessed, and in the event of a significant negative impact on Natura 2000 the project may be rejected or require changes.

The Nature Conservation Act and the regulations on environmental impact assessments require an analysis of the impact of the planned project on species and habitats, also outside the boundaries of the area, if the impact may reach there. The impact may concern noise, odour emissions, dust, vehicle traffic, discharge of water and effects on animals. The authority may impose conditions, e.g. restrictions on work during the breeding season. Consultations with the regional directorate for environmental protection make it possible to identify risks early. This is general information.

Sources: Ustawa o ochronie przyrody — ISAP; Ustawa o udostępnianiu informacji o środowisku (oceny oddziaływania na środowisko) — ISAP

Link to this answer

Can a biogas plant be built near my home?

Yes, it can, if the investor has a location consistent with the plan or with a decision on development conditions and obtains the required decisions, but residents have the right to information and to take part in the environmental procedure and may submit comments.

The possibility of a location is decided, among other things, by the local spatial development plan or a decision on development conditions, as well as by an analysis of nuisances (odour, noise, lorry traffic, safety). The regulations do not set a single, nationwide minimum distance of all biogas plants from residential buildings – nor did the Act of 13 July 2023 on facilitating the preparation and implementation of agricultural biogas plant investments (Journal of Laws (Dz.U.) 2023, item 1597) introduce one; distance requirements result from local plans, the environmental decision and technical and fire regulations, so it is worth checking the documents at the municipality. Good practice is for the investor to talk to residents early. This is general information, not legal advice.

Sources: Ustawa o planowaniu i zagospodarowaniu przestrzennym — ISAP; Ustawa o udostępnianiu informacji o środowisku (oceny oddziaływania na środowisko) — ISAP; Ustawa Prawo ochrony środowiska — ISAP; Ustawa z 13 lipca 2023 r. o ułatwieniach w przygotowaniu i realizacji inwestycji w zakresie biogazowni rolniczych (Dz.U. 2023 poz. 1597) — ELI

Link to this answer

Can a biogas plant be built on agricultural land?

It can, but changing the designation of agricultural land to non-agricultural purposes is subject to the Act on the Protection of Agricultural and Forest Land, and for land of higher soil-quality classes it usually requires the consent of the competent authority.

Protection applies especially to land of the best classes, and for lower classes the procedure is sometimes simpler. In practice admissibility is decided by the local plan or a decision on development conditions, and the investor may be required to pay charges and annual fees for removing the land from production. Biogas plants are often located near farms or processing plants, on already developed land, which simplifies formalities. The detailed classes and procedures must be checked in the Act and at the municipality. This is general information.

Sources: Ustawa o ochronie gruntów rolnych i leśnych — ISAP; Ustawa o planowaniu i zagospodarowaniu przestrzennym — ISAP

Link to this answer

Can a biogas plant hold certification in both ISCC and REDcert at the same time?

The rules depend on the schemes'' regulations and the certification body; in practice, one scheme is chosen for a given supply chain to avoid ambiguity in the mass balance and double counting of batches.

Sources: Dyrektywa (UE) 2018/2001 (RED II), art. 30 — EUR-Lex; ISCC System GmbH; REDcert GmbH

Discussed in the article: ISCC EU vs REDcert2 certification for biogas plants: a comparison of the systems

Link to this answer

Can a gas grid operator refuse to connect a biomethane plant?

The operator may refuse to conclude a connection agreement where there are no technical or economic conditions for connection or the applicant does not meet the connection conditions, and it must give reasons; a dispute can be resolved by the President of URE.

This follows from the Energy Law rules on connection to the grid and access to it. A typical cause of restrictions is a lack of absorption capacity in the grid at a given location, especially in summer, when gas consumption is low, or the high cost of expanding the grid. The investor should submit an application for connection conditions early, analyse the operator's response and, in case of doubt, use the dispute route before URE. In practice the solution is sometimes to change the entry point, expand the grid or use a shared injection point. This is general information, not legal advice.

Sources: Ustawa Prawo energetyczne (Dz.U. 1997 nr 54 poz. 348) — ISAP; Urząd Regulacji Energetyki

Link to this answer

Can a new biogas plant in Latvia receive OIK?
Can an agricultural biogas plant of up to 1 MW take part in an auction at all?

Yes. The Act provides for separate auctions for installations with a capacity of no more than 1 MW and for larger ones, and within agricultural biogas it sets out baskets below 500 kW and from 500 kW to 1 MW.

Sources: Ustawa o odnawialnych źródłach energii z 20 lutego 2015 r. — tekst jednolity (Dz.U. 2022 poz. 1378); Urząd Regulacji Energetyki — strona główna

Discussed in the article: RES auctions for biogas plants: who can take part, what documents and security are needed

Link to this answer

Can an information sheet be submitted instead of a report?

For projects that always have a significant impact, the applicant may submit an information sheet together with a request to determine the scope of the report (Article 69). The report must then be submitted after the decision on the scope has been issued.

Sources: Ustawa z 3 października 2008 r. o udostępnianiu informacji o środowisku (ustawa ooś) — Internetowy System Aktów Prawnych

Discussed in the article: Environmental impact report for a biogas plant: what it must contain (Article 66 of the Environmental Impact Assessment Act)

Link to this answer

Can biomethane supported by URE count towards the NCW?

No. Article 83s of the Act on Renewable Energy Sources (ustawa o OZE) excludes from meeting the NCW biomethane that receives support under Chapter 4a, and the Act of 4 September 2026 extends this rule to support from biomethane auctions.

Sources: Dyrektywa (UE) 2023/2413 (RED III) — EUR-Lex; Ustawa o biokomponentach i biopaliwach ciekłych — tekst jednolity z lipca 2025 r. (Dz.U. 2025 poz. 901); Ustawa z 4 września 2026 r. o zmianie ustawy o OZE (Dz.U. 2026 poz. 1347)

Discussed in the article: Biomethane in transport: the NCW, RED III and what it means for bioCNG and bioLNG in 2026

Link to this answer

Can digestate be spread on fields in winter?
Can digestate from sewage sludge bear the CE marking?

Not on the basis of CMC 5 or CMC 3: sewage sludge, industrial sludge and dredging sludge are not an approved input material for compost and digestate under this regulation.

Sources: Rozporządzenie (UE) 2019/1009 — produkty nawozowe UE (EUR-Lex); Ustawa z dnia 10 lipca 2007 r. o nawozach i nawożeniu — tekst jednolity z 2024 r. (ISAP/ELI)

Discussed in the article: Regulation 2019/1009: digestate as an EU fertilising product with the CE marking

Link to this answer

Can a penalty decision be appealed?

Yes. A decision of the Voivodeship Inspectorate for Environmental Protection (WIOŚ) can be appealed to the Chief Inspector for Environmental Protection, a decision of the Director General of KOWR to the minister responsible for agricultural markets, and a decision of the President of the Energy Regulatory Office (URE) to the Court of Competition and Consumer Protection.

Sources: Ustawa z 14 grudnia 2012 r. o odpadach (rozdz. 2 – administracyjne kary pieniężne) — Internetowy System Aktów Prawnych; Ustawa z 20 lutego 2015 r. o odnawialnych źródłach energii (art. 168–176) — Internetowy System Aktów Prawnych; Krajowy Ośrodek Wsparcia Rolnictwa

Discussed in the article: Liability and penalties: what a biogas plant risks for breaching regulations

Link to this answer

Can you get a subsidy for electricity from biogas under SDE++?

Yes, for cogeneration in all-feedstock digestion and in slurry mono-digestion, if its nominal electrical efficiency is at least 20%.

Sources: RVO — SDE++: Hernieuwbare warmte; RVO — SDE++: Hernieuwbaar gas; PBL — Advies basisbedragen SDE++ 2026 (13.02.2026)

Discussed in the article: Netherlands: SDE++ and electricity from biogas and biomass — cogeneration, heat and slurry mono-digestion

Link to this answer

Can you still get a tariff in France for electricity from a new biogas plant?
Could a biogas plant take part in the Lithuanian auction?
Did RESS replace REFIT tariffs for biogas plants?
Do biogas plants count towards waste recycling?
Do biogas plants pay for CO₂ emissions under the EU ETS?

The vast majority of biogas plants are not subject to the EU ETS, because the system covers combustion installations with a total thermal capacity above 20 MW, and emissions from burning biomass that meets the sustainability and greenhouse gas reduction criteria are treated as zero.

Agricultural biogas plants usually have a cogeneration capacity counted in single megawatts, so they are below the threshold. Even when an installation is covered by the system, emissions from biomass and biogas that comply with the criteria do not require the surrender of allowances. These rules result from Directive 2003/87/EC and the implementing acts on emissions monitoring. For a biogas plant, the RED sustainability criteria are more important than the ETS if it is to sell biomethane or use support. You determine the specific status of an installation after checking the greenhouse gas emission permit and the regulations. This is general information.

Sources: Dyrektywa 2003/87/WE (EU ETS) — EUR-Lex; Dyrektywa (UE) 2023/2413 (RED III) — EUR-Lex; Rozporządzenie wykonawcze (UE) 2018/2066, art. 38 ust. 5 — EUR-Lex

Link to this answer

Do the CEEAG affect Polish RES auctions?

Yes, indirectly. The Commission assesses every renewable energy aid scheme requiring notification against the CEEAG, so the rules for tenders, premiums and exemptions for small installations must fit within them.

Sources: Covington — The Commission adopts its new Climate, Energy and Environmental Aid Guidelines (CEEAG) (8.02.2022); CMS — The European Commission has endorsed its new CEEAG 2022; Komisja Europejska — State aid, strona główna polityki konkurencji

Discussed in the article: CEEAG 2022 Guidelines: new state aid rules for energy and climate — what they mean for biogas and biomass

Link to this answer

Do the changes concern biogas?
Do the GGSS rates from October 2025 apply all year?
Does a 2 MW agricultural biogas plant need a licence for electricity generation?

No. Generating electricity from agricultural biogas is exempt from the licensing obligation regardless of capacity, but the activity requires an entry in the register of agricultural biogas producers kept by KOWR.

Sources: Prawo energetyczne — tekst jednolity z 2021 r. (Dz.U. 2021 poz. 716), art. 32; Ustawa o odnawialnych źródłach energii — tekst jednolity (Dz.U. 2022 poz. 1378); Urząd Regulacji Energetyki — strona główna

Discussed in the article: URE licence or register entry? When a biogas plant needs a licence

Link to this answer

Does a biogas plant below 0.5 MW not need an environmental decision?

An agricultural biogas plant with an electrical capacity of up to 0.5 MW is excluded from the regulation's listings on fuel production and waste processing, but other elements of the investment (e.g. fuel combustion, a gas pipeline) and a location in a Natura 2000 area may require an assessment. Always check the whole catalogue.

Sources: Rozporządzenie Rady Ministrów z 10 września 2019 r. w sprawie przedsięwzięć mogących znacząco oddziaływać na środowisko — Internetowy System Aktów Prawnych; Ustawa z 3 października 2008 r. o udostępnianiu informacji o środowisku (ustawa ooś) — Internetowy System Aktów Prawnych

Discussed in the article: Environmental decision for biogas plants: when and how to obtain it

Link to this answer

Does a biogas plant need a licence from the President of URE?

It depends on what it produces and at what scale: producing agricultural biogas is a regulated activity (entry in the KOWR register), and URE licences concern selected types of energy activity, so this has to be assessed for the specific project.

The Energy Law (Article 32) requires a licence for some types of activity, such as generating electricity in sources exceeding certain capacity thresholds or trading in gaseous fuels, and also provides exemptions for small installations and micro-installations. Agricultural biogas and biomethane also have their own rules in the Act on Renewable Energy Sources (ustawa o OZE). We do not rely here on a single threshold, because the regulations have been amended many times. Before launching a project, check with a lawyer or with URE whether a licence or an entry is needed for your installation and sales model. This is general information, not legal advice.

Sources: Ustawa Prawo energetyczne (Dz.U. 1997 nr 54 poz. 348) — ISAP; Urząd Regulacji Energetyki

Link to this answer

Does a guarantee of origin confirm the sustainability of biomethane?
Does an agricultural biogas plant running on slurry also need veterinary approval?

As a rule, yes, because slurry and manure are Category 2 material (Article 9(a) of Regulation 1069/2009), and converting animal by-products (UPPZ) into biogas requires approval. Establish the details in a specific case with the district veterinary officer.

Sources: Rozporządzenie (WE) nr 1069/2009 — art. 24 i 44 (EUR-Lex); Rozporządzenie Komisji (UE) nr 142/2011 — załącznik V (EUR-Lex); Główny Inspektorat Weterynarii — strona instytucji

Discussed in the article: Approval of a biogas plant by the County Veterinary Officer: the procedure step by step

Link to this answer

Does changing substrates in a biogas plant require changing permits?

Often yes: a new type of substrate, especially waste, may require a change to the waste processing permit or the BDO entry, and for larger changes also a change to the environmental decision, the permit or the entry in the agricultural biogas register.

Each type of waste has a code from the waste catalogue and must be included in the installation's documents. A change in the proportions of substrates may affect emissions, the amount of digestate, the demand for storage and sanitary requirements. In the case of agricultural biogas and support, there are restrictions on permitted substrates, the breach of which may result in loss of entitlements. Therefore, before changing the recipe, check whether the new material is covered by the permits and, if in doubt, consult the authority or an adviser. This is general information.

Sources: Ustawa o odpadach (Dz.U. 2013 poz. 21) — ISAP; Ustawa Prawo ochrony środowiska — ISAP

Link to this answer

Does Lei 14.300 apply only to photovoltaics?

No. The Act covers micro- and mini-generation from renewable sources and qualified cogeneration, so also biogas and biomass installations. In practice most installations are photovoltaic.

Sources: Money Times — Marco legal da geração distribuída é sancionado com vetos; Mayer Brown — Informativo do Setor Elétrico: Lei nº 14.300/2022 (styczeń 2022)

Discussed in the article: Brazil: Lei 14.300 sets order in distributed generation, and the Fio B charge rises gradually until 2028

Link to this answer

Does RED II prohibit fixed tariffs (FIT)?

The directive does not use that name, but it requires support schemes to encourage responsiveness to market prices and integration with the energy market. In practice this means premiums on top of the market price and auctions, with exceptions for small installations.

Sources: Dyrektywa (UE) 2018/2001 — EUR-Lex; Komisja Europejska — Renewable energy directive

Discussed in the article: RED II and electricity support: market premiums, auctions and protection against retroactive changes

Link to this answer

Does RED III apply directly to biogas plants?

The directive must be transposed into national law, so obligations for biogas plants arise from national regulations. Already now, however, it is worth reckoning with stricter emission and certification criteria, which apply to the sale of biomethane as a renewable fuel.

The obligations of operators arise from national regulations and from directly applicable regulations and implementing acts.

Sources: Dyrektywa (UE) 2023/2413 (RED III) — EUR-Lex; Dyrektywa (UE) 2018/2001 (RED II) — EUR-Lex; Ministerstwo Klimatu i Środowiska

Discussed in the article: RED III: what it changes for biogas and biomethane – analysis and the state of implementation in Poland

Link to this answer

Does RED III change the requirements for small biogas plants?

Not for biogas: the threshold for applying sustainability criteria to gaseous fuels remains at 2 MW. The reduction from 20 MW to 7.5 MW applies to solid fuels, that is, biomass heat and power plants.

Sources: Dyrektywa (UE) 2023/2413 — EUR-Lex; EEB — RED timeline guidance: transposition and implementation deadlines

Discussed in the article: RED III transposition deadline passed (21 May 2025): sustainability thresholds for biogas and biomass

Link to this answer

Does SEG guarantee a fixed price for energy from biogas plants?

No. Unlike FIT, there is no centrally set rate: energy suppliers set their own export tariffs, so the generator compares offers and negotiates.

Sources: Ofgem — SEG: wytyczne dot. kryteriów zrównoważenia dla biogazu; Addleshaw Goddard — Smart Export Guarantee (2020)

Discussed in the article: United Kingdom: the Smart Export Guarantee replaces FIT, and biogas plants face an audit

Link to this answer

Does the amendment raise the premium rate for biogas plants?

According to the Commission's announcement, the amendment concerns an increase in the budget of the scheme, and the premium for renewable energy, including from cogeneration, is €53.7/MWh.

Sources: Komisja Europejska — State aid: Commission approves amendment to Estonian scheme to support electricity production from renewables (19.06.2023)

Discussed in the article: Estonia: Commission approves amendment to premium scheme (SA.102228), budget rises to €1.37 billion

Link to this answer

Does the decision concern biogas plants?

The Commission's communication describes the scheme in general terms, as support for electricity from renewable sources. Biogas and biomass take part in Polish auctions, which operate within this scheme.

Sources: Komisja Europejska — Commission approves prolongation of Polish aid scheme to support electricity production (30.11.2021)

Discussed in the article: Commission extends the Polish RES auction scheme for 2022–2027 (SA.64713)

Link to this answer

Does the EU Methane Regulation cover biogas plants?

Regulation (EU) 2024/1787 concerns mainly the fossil fuel sector (oil, natural gas, coal), not agricultural biogas plants, but biomethane injected into the gas grid benefits from similar standards for measuring and limiting leaks.

The act sets out rules for measuring, reporting and verifying methane emissions and for reducing them, including detecting and repairing leaks, restrictions on flaring and venting of gas, and requirements for imports. The Regulation (Article 1(2)) covers oil, natural gas and coal and does not mention biogas plants, so producers should check their status in the text of the Regulation and in national provisions. In practice, good leak-control practices result in any case from safety and economics: escaping methane is a loss of product. This is general information, not legal advice.

Sources: Rozporządzenie (UE) 2024/1787 w sprawie redukcji emisji metanu w sektorze energii — EUR-Lex; IEA — Global Methane Tracker 2025

Link to this answer

Does the law restrict the use of energy crops in biogas plants?

Yes, EU law limits the counting of biofuels from food and feed crops towards transport targets, and support schemes and sustainability criteria favour waste, residues and slurry.

The RED Directive sets limits on the share of biofuels from crops that may be counted towards the transport target, and requires demonstrating that the feedstocks do not come from land of high biodiversity, land with high carbon stock or from peatlands. Biogas plants running on maize silage can operate lawfully, but their product may be less attractive to the advanced fuels market, and national support mechanisms may have their own substrate limits. Investors therefore increasingly base projects on slurry, manure and waste. Check the specific limits and permitted substrates in the current national regulations and certification requirements. This is general information.

Sources: Dyrektywa (UE) 2023/2413 (RED III) — EUR-Lex; Dyrektywa (UE) 2018/2001 (RED II) — EUR-Lex

Link to this answer

Does the methane regulation impose obligations on agricultural biogas plants?

The regulation concerns the fossil fuel sector: oil, natural gas and coal. The Commission's website does not list biogas or biomethane among the sectors covered, and indirect effects may concern gas infrastructure and the gas market.

Sources: Rozporządzenie (UE) 2024/1787 w sprawie redukcji emisji metanu w sektorze energii — EUR-Lex; Komisja Europejska — emisje metanu w sektorze energii

Discussed in the article: EU Methane Regulation 2024/1787: obligations for the energy sector and significance for biogas

Link to this answer

Does the nitrates programme apply only in vulnerable zones?

No. The programme adopted in February 2020 applies throughout the country. Earlier programmes applied only to areas particularly vulnerable to nitrate pollution.

Sources: Rozporządzenie Rady Ministrów z 12 lutego 2020 r. w sprawie przyjęcia Programu działań azotanowych (Dz.U. 2020 poz. 243); Dyrektywa Rady 91/676/EWG (dyrektywa azotanowa) — EUR-Lex

Discussed in the article: Nitrates programme 2020: the 170 kg N/ha limit, fertilising dates and tanks, and digestate

Link to this answer

Does the UDB replace an ISCC or REDcert certificate?

No. The certificate confirms compliance with sustainability criteria, while the UDB serves to track batches and transactions. The data in the database often come from certification systems.

Sources: Dyrektywa (UE) 2018/2001 (RED II) — EUR-Lex; Rozporządzenie wykonawcze Komisji (UE) 2022/996 — EUR-Lex; Komisja Europejska – Dyrekcja Generalna ds. Energii

Discussed in the article: Union Database (UDB): tracking biomethane and renewable fuels in the EU

Link to this answer

Has Poland transposed the RED III Directive?

Poland is implementing RED III in stages, through several acts, and the transposition deadline (21 May 2025) has passed; the European Commission is urging Member States, including Poland, to fully implement the renewable energy provisions.

Directive (EU) 2023/2413 entered into force on 20 November 2023, and Member States were to implement it by 21 May 2025 (for Article 15e and Articles 16, 16b–16f of Directive 2018/2001 as worded in RED III, the deadline was 1 July 2024). In Poland the provisions are entering the legal order through several acts, including the amendment to the Act on Renewable Energy Sources (ustawa o OZE) (with biomethane and guarantees of origin) and drafts concerning fuels and biocomponents in transport. The state of work is changing quickly and not all elements of RED III had been implemented as of October 2026. For this reason, in investment projects distinguish EU targets from national provisions actually in force and check the current state in the Journal of Laws (Dziennik Ustaw) and on the RCL. This is general information.

Sources: Dyrektywa (UE) 2023/2413 (RED III) — EUR-Lex; Ministerstwo Klimatu i Środowiska

Link to this answer

How are GGSS rates indexed?

Automatically on 1 April each year, according to the percentage change in the CPI consumer price index from the previous calendar year.

Sources: GOV.UK — Green Gas Support Scheme (GGSS): Annual Tariff Review 2023; GOV.UK — Green Gas Support Scheme (GGSS): Annual Tariff Review 2022

Discussed in the article: United Kingdom: the 2023 GGSS review raises the Tier 3 rate from 1.72 to 3.45 p/kWh

Link to this answer

How can residents submit comments on a planned biogas plant?

Residents can submit comments and requests in the procedure for issuing an environmental decision, which is public and includes public participation, and persons who are parties may also take part in the building permit procedure.

Notices of the initiation of proceedings are published in the Public Information Bulletin (Biuletyn Informacji Publicznej, BIP), on notice boards and in the manner customary in the municipality, and comments must be submitted by the set deadline. Specific comments are valuable: about odour, noise, traffic, water, safety and the impact on buildings. The authority is obliged to consider them and justify its decisions. Residents can also approach the municipality about the local plan. The detailed rights of parties depend on their location and the way they are affected. This is general information, not legal advice.

Sources: Ustawa o udostępnianiu informacji o środowisku (oceny oddziaływania na środowisko) — ISAP; Ustawa Prawo budowlane — ISAP

Link to this answer

How is biomethane sustainability certified in Poland?

The sustainability of biomethane is confirmed in a voluntary scheme recognised by the European Commission, such as ISCC EU, REDcert-EU or the Polish KZR INiG, in which a certification body audits the supply chain from feedstock to sale.

The certificate covers the feedstock producer, the biogas or biomethane plant and the subsequent links in the chain, and the company documents batches, the mass balance and emission calculations. Operators enter supply data into the Union Database for Biofuels, which is meant to limit the risk of double counting. The choice of scheme depends on the target market and customers' requirements, and costs include audits and implementing a documentation system. KZR INiG is a national scheme run by the Oil and Gas Institute (Instytut Nafty i Gazu); check the current requirements in the scheme's documents.

Sources: ISCC — International Sustainability and Carbon Certification; Instytut Nafty i Gazu — Państwowy Instytut Badawczy; Komisja Europejska: Union Database for Biofuels — materiały szkoleniowe

Link to this answer

How long is an environmental decision valid?

This depends on the provisions of the Act on Environmental Impact Assessments (ustawa ooś) on time limits and on amending the decision, and on its content. The details must be checked in the current consolidated text, because the provisions have been amended.

Sources: Rozporządzenie Rady Ministrów z 10 września 2019 r. w sprawie przedsięwzięć mogących znacząco oddziaływać na środowisko — Internetowy System Aktów Prawnych; Ustawa z 3 października 2008 r. o udostępnianiu informacji o środowisku (ustawa ooś) — Internetowy System Aktów Prawnych

Discussed in the article: Environmental decision for biogas plants: when and how to obtain it

Link to this answer

How long is the support period in YEKDEM under Decision No 3453?

10 years from the start of operation of the installation. For the price with a local component, five years and a supplement of 0.08 TL/kWh are provided.

Sources: Legal 500 — New tariff in YEKDEM and local content prices (decyzja nr 3453); Anadolu Agency — Turkey extends renewable energy support mechanism date

Discussed in the article: Turkey: YEKDEM reworked — biogas at 0.54 TL/kWh, lira rates with a USD cap

Link to this answer

What is the most an Estonian generator can earn from one MWh?

According to the description of the scheme, total revenue from the market and the premium is approx. €93/MWh when the market price is in the range €39.3–93/MWh: the premium base is €53.7/MWh, but above €39.3/MWh the premium declines, and at approx. €93/MWh it is zero. Above €93/MWh the generator receives the full market price, that is, more.

Sources: IEA — Estonia: Amendments to the Electricity Market Act establishing reverse auctions and sliding premium; pv magazine — Estonia launches competitive renewables auctions (22.11.2019); Elering — Renewable energy charge returns to 2017 level (grudzień 2018)

Discussed in the article: Estonia: sliding premium of €53.7/MWh for 12 years for energy from biogas and biomass

Link to this answer

How much could the premium for a Finnish biogas plant have been?

With an average market price below €30/MWh, the premium was €53.50/MWh (83.50 minus 30). At a price of €60/MWh it was €23.50/MWh, and above €83.50/MWh the premium fell to zero. On top of this came €50/MWh for heat from cogeneration.

Sources: IEA — Feed-in Tariffs for electricity from wind, biogas and wood chip (Finlandia); Clean Energy for EU Islands — Finlandia: premium tariff (premia ciepłowa); Clean Energy for EU Islands — Finlandia: tender-based premium scheme

Discussed in the article: Finland: target price premium of €83.50/MWh for biogas and its closure in 2019

Link to this answer

How much is 74.5 øre/kWh in euro?
How does RED III change the GHG emission saving thresholds?

For electricity, heating and cooling from biomass in new installations (after 20 November 2023) the required reduction is 80%; for installations commissioned earlier, transitional periods are provided, depending on capacity and date of commissioning.

Sources: Dyrektywa (UE) 2023/2413 (RED III) — EUR-Lex; Dyrektywa (UE) 2018/2001 (RED II) — EUR-Lex; Ministerstwo Klimatu i Środowiska

Discussed in the article: RED III: what it changes for biogas and biomethane – analysis and the state of implementation in Poland

Link to this answer

How do you calculate the maximum slurry dose per hectare?

By dividing 170 kg N/ha by the nitrogen content of the slurry. Example: at 4 kg N/m³ it comes to 42.5 m³/ha a year. The N content is taken from the annex to the programme or from a laboratory test.

Sources: Rozporządzenie Rady Ministrów z 12 lutego 2020 r. w sprawie przyjęcia Programu działań azotanowych (Dz.U. 2020 poz. 243); Dyrektywa Rady 91/676/EWG (dyrektywa azotanowa) — EUR-Lex

Discussed in the article: Nitrates programme 2020: the 170 kg N/ha limit, fertilising dates and tanks, and digestate

Link to this answer

Is a biogas plant subject to the rules on major accidents (Seveso)?

The Seveso rules apply to establishments in which the quantity of hazardous substances reaches or exceeds the thresholds in Directive 2012/18/EU, so some large biogas and biomethane plants may be classified, while smaller ones usually are not.

Biogas and methane are flammable gases, and the total quantity of hazardous substances on the site is assessed, including stored gas, oil or chemicals. An establishment that exceeds the thresholds is classified as an establishment with an increased or high risk of a major industrial accident and has additional obligations, e.g. concerning an accident prevention programme and notifications. Classification is carried out for the whole establishment (the area under the operator's control, together with its installations), and in Poland the provisions were implemented in the Environmental Protection Law. This is general information.

Sources: Dyrektywa 2012/18/UE (Seveso III) — EUR-Lex; Ustawa Prawo ochrony środowiska — ISAP

Link to this answer

Is a certificate the same as an administrative permit?

No. A certificate is a private-law document of a voluntary scheme that confirms compliance with the criteria; it does not replace environmental permits, a building permit or registration with KOWR.

Sources: Dyrektywa (UE) 2018/2001 (RED II), art. 30 — EUR-Lex; ISCC System GmbH; REDcert GmbH

Discussed in the article: ISCC EU vs REDcert2 certification for biogas plants: a comparison of the systems

Link to this answer

Is a default value enough instead of calculations?

Yes, if a default value exists for the given production pathway in Annex V or VI and the conditions for its use are met. Default values are conservative, so a well-run plant often achieves a better result from actual calculations.

Sources: Dyrektywa (UE) 2018/2001 (RED II) — EUR-Lex; Rozporządzenie wykonawcze Komisji (UE) 2022/996 — EUR-Lex (aktualizacja)

Discussed in the article: GHG emission reduction under RED II: thresholds, default values and calculations for biogas

Link to this answer

Is a local plan needed to build a biogas plant, or are development conditions enough?

The location of a biogas plant is decided by the local spatial development plan or, where there is no plan, by a decision on development conditions or another location decision, and the scope depends on the type of investment and the regulations in force.

In Poland the spatial planning system is changing as part of a reform (general plans of municipalities), so it is worth checking the situation in the specific municipality. On agricultural land, good soil-quality classes are protected by the Act on the Protection of Agricultural and Forest Land, so a change of designation often requires consent. For agricultural biogas plants covered by the Act of 13 July 2023 on facilitating the preparation and implementation of agricultural biogas plant investments (Article 4(1)), the location can be determined by a municipal council resolution establishing the location of an agricultural biogas plant, even without a local plan, provided it does not conflict with the municipality's study of spatial development conditions and directions (Article 19(4)–(5)). The investor should start with an extract from the plan or an application for development conditions. This is general information, not legal advice.

Sources: Ustawa o planowaniu i zagospodarowaniu przestrzennym — ISAP; Ustawa o ochronie gruntów rolnych i leśnych — ISAP; Ustawa z 13 lipca 2023 r. o ułatwieniach w przygotowaniu i realizacji inwestycji w zakresie biogazowni rolniczych, Dz.U. 2023 poz. 1597

Link to this answer

Is adjacent development needed to issue a WZ decision for a biogas plant?

Under the legal situation of 2021, no: for RES installations the requirement of good neighbourhood and access to a public road was abolished, but the other conditions under Article 61(1) must still be met.

Sources: Ustawa o planowaniu i zagospodarowaniu przestrzennym — Internetowy System Aktów Prawnych; Ustawa z 13 lipca 2023 r. o ułatwieniach w inwestycjach w zakresie biogazowni rolniczych — Dziennik Ustaw

Discussed in the article: Zoning decision or local plan (MPZP)? Siting a biogas plant in spatial planning

Link to this answer

Is an environmental decision needed to build a biogas plant?

In many cases yes: depending on their size and the type of substrates processed, biogas plants qualify as projects that may always or potentially have a significant impact on the environment, which requires a decision on environmental conditions.

The catalogue of such projects is set out in the Council of Ministers regulation of 10 September 2019 (Journal of Laws (Dz.U.) 2019, item 1839). For projects that "always have a significant impact", the authority requires an environmental impact report, while for those that "potentially have a significant impact" it decides after analysing an information sheet. The parties and the public take part in the procedure, which is why consultations and comments from residents often arise. The specific thresholds and classification depend on the project and must be checked in the current wording of the regulations. This is general information, not legal advice.

The decision on environmental conditions must be issued before the building permit, and the authority checks that the project complies with its conditions.

Sources: Ustawa o udostępnianiu informacji o środowisku (oceny oddziaływania na środowisko) — ISAP; Rozporządzenie RM w sprawie przedsięwzięć mogących znacząco oddziaływać na środowisko (Dz.U. 2019 poz. 1839) — ISAP; Ustawa z 7 lipca 1994 r. – Prawo budowlane — Internetowy System Aktów Prawnych; Główny Urząd Nadzoru Budowlanego

Discussed in the article: Building permit for a biogas plant step by step: from design to occupancy permit

Link to this answer

Is an occupancy permit always needed after construction is completed?

Not always. For many facilities, a notification of completion of construction is sufficient, but for the categories listed in Article 55(1) of the Construction Law, a decision granting an occupancy permit is required. The category of each facility in the complex must be checked.

Sources: Ustawa z 7 lipca 1994 r. – Prawo budowlane — Internetowy System Aktów Prawnych; Główny Urząd Nadzoru Budowlanego

Discussed in the article: Building permit for a biogas plant step by step: from design to occupancy permit

Link to this answer

Is mixing slurry with kitchen waste allowed?

Yes, but a mixture of Category 2 and Category 3 material is classified as Category 2, and the authority may approve the treatment parameters for mixtures with manure as alternative ones. This requires agreement as part of the plant approval.

Sources: Rozporządzenie (WE) nr 1069/2009 — art. 9, 10, 13, 21 (EUR-Lex); Rozporządzenie Komisji (UE) nr 142/2011 — załącznik V (EUR-Lex)

Discussed in the article: Manure, slurry and catering waste in a biogas plant and the UPPZ rules

Link to this answer

Is the connection advance payment refundable?

Under the legal situation at the beginning of 2024, the advance was credited towards the connection fee; if it exceeded the fee, the difference was refunded with statutory interest. After the 2026 changes, a non-refundable fee for processing the application is added.

Sources: Ustawa z 10 kwietnia 1997 r. – Prawo energetyczne (art. 7) — Internetowy System Aktów Prawnych; Urząd Regulacji Energetyki

Discussed in the article: Connecting a biogas plant to the electricity grid: conditions, advance payment, contract, stages

Link to this answer

Is the EN 16723 standard mandatory in Poland?

The standard itself is voluntary. The legally binding requirements are the parameters in the ordinance on the functioning of the gas system and the operator's requirements set out in the connection conditions and the contract. The standard is often used as a technical reference point.

Sources: Rozporządzenie Ministra Gospodarki z 2 lipca 2010 r. w sprawie szczegółowych warunków funkcjonowania systemu gazowego — Internetowy System Aktów Prawnych; Urząd Regulacji Energetyki; Ustawa z 20 lutego 2015 r. o odnawialnych źródłach energii (art. 118) — Internetowy System Aktów Prawnych

Discussed in the article: Biomethane quality in the gas grid: the parameters in the regulation and who checks them

Link to this answer

Is the programme intended for biogas plants?

The programme covers high-efficiency cogeneration fuelled by various fuels, including biogas and biomass. It is not a programme dedicated solely to biogas, and natural gas remains one of the permitted fuels.

Sources: IEU Monitoring — Spain: EU Commission approves €3.1bn State aid to support cogenerated electricity (28.01.2026); Brussels Times — EU okays Spain's €3.1b state aid support for cogenerated electricity

Discussed in the article: Commission approves EUR 3.1 billion for Spanish cogeneration, including on biogas and biomass (SA.114058)

Link to this answer

Is this support for biogas plants?

Not directly. Scheme SA.55891 concerns existing biomass power plants and combined heat and power plants that could return to fossil fuels. Biogas in Denmark has a separate support system.

Sources: Komisja Europejska — Commission approves €550 million Danish scheme to support electricity production from biomass (19.05.2020)

Discussed in the article: Denmark: Commission approves DKK 4.15 billion for existing biomass power plants (SA.55891)

Link to this answer

May municipal waste be added to an agricultural biogas plant?

No, if the installation is to produce agricultural biogas. Biogas obtained from municipal waste, from landfills and from substrates from wastewater treatment plants (except for on-site treatment plants of agri-food processing with separation of wastewater) is not agricultural biogas.

Sources: Ustawa o odnawialnych źródłach energii — tekst jednolity z 2024 r. (Dz.U. 2024 poz. 1361), art. 2, 25, 30; Ustawa o OZE — tekst jednolity z 2026 r. (Dz.U. 2026 poz. 68)

Discussed in the article: Agricultural biogas in the Act on Renewable Energy Sources: definition, permitted substrates and what does not count

Link to this answer

Must a biogas combined heat and power plant buy emission allowances for CO₂?

Only if the total rated thermal input of combustion in the installation exceeds 20 MW. Below that threshold there is no obligation, and emissions from biogas that meets the sustainability criteria are treated as zero-emission in the ETS.

Sources: Dyrektywa 2003/87/WE (EU ETS) — EUR-Lex; Dyrektywa (UE) 2018/2001 (RED II) — EUR-Lex; Komisja Europejska — monitorowanie, raportowanie i weryfikacja emisji w EU ETS

Discussed in the article: ETS and biogas plants: do you need to buy CO₂ emission allowances

Link to this answer

Must a biogas plant belong to an energy cooperative or cluster?
Must a biogas plant meet the National Indicative Target?

No. The obligation rests on entities that produce, import or acquire intra-Community liquid fuels and liquid biofuels and dispose of them in Poland. A biogas plant can be a biomethane supplier for such companies.

Sources: Ustawa o biokomponentach i biopaliwach ciekłych — tekst jednolity z maja 2019 r. (Dz.U. 2019 poz. 1155); Dyrektywa (UE) 2018/2001 (RED II) — EUR-Lex; KOWR — wytwórcy biokomponentów i biopaliw ciekłych

Discussed in the article: National Indicative Target (NCW): who it applies to and where biomethane fits

Link to this answer

Must a biogas plant itself undergo an audit under this regulation?

The regulation sets the verification rules, and the certificate is issued by a certification body within a recognised voluntary or national scheme. The details depend on whether the installation falls within the scope of Article 29 of RED II.

Sources: Rozporządzenie wykonawcze (UE) 2022/996 — EUR-Lex; EUR-Lex — podsumowanie: kryteria zrównoważenia i redukcji emisji

Discussed in the article: Implementing Regulation 2022/996: how the sustainability of biogas and biomass is verified, mass balance

Link to this answer

Must a biomethane producer selling gas to the grid enter data in the UDB?

It depends on national regulations and on whether biomethane is counted as a renewable fuel under the targets. In Poland, the obligation to submit data applies, among others, to producers and processors under the Act on Biocomponents and Liquid Biofuels.

Sources: Dyrektywa (UE) 2018/2001 (RED II) — EUR-Lex; Rozporządzenie wykonawcze Komisji (UE) 2022/996 — EUR-Lex; Komisja Europejska – Dyrekcja Generalna ds. Energii

Discussed in the article: Union Database (UDB): tracking biomethane and renewable fuels in the EU

Link to this answer

Must an agricultural biogas plant running on slurry meet the land criteria of Article 29?

Slurry is an agricultural residue, so checking the status of the cultivation land does not apply to it, but plans or measures protecting soil quality and carbon stocks are required, as is meeting the GHG emission reduction threshold.

Sources: Dyrektywa (UE) 2018/2001 (RED II) — EUR-Lex; Ustawa o odnawialnych źródłach energii z 2015 r. — Internetowy System Aktów Prawnych

Discussed in the article: RED II and biogas plants: sustainability and emission-reduction criteria (Article 29)

Link to this answer

Must a small agricultural biogas plant calculate GHG emission savings under RED II?

According to the Directive, the criteria for biogas used in electricity and heat apply from 2 MW of installation thermal capacity, but Member States may extend them to smaller ones. When biogas or biomethane is sold for transport, they apply regardless of capacity.

Sources: Dyrektywa (UE) 2018/2001 (RED II) — EUR-Lex; Rozporządzenie wykonawcze Komisji (UE) 2022/996 — EUR-Lex (aktualizacja)

Discussed in the article: GHG emission reduction under RED II: thresholds, default values and calculations for biogas

Link to this answer

Must a biomethane producer using agricultural biogas also be entered in the URE register?

No, if the biomethane is produced exclusively from agricultural biogas – then an entry in the register of agricultural biogas producers at KOWR is sufficient. Biomethane from biogas other than agricultural, and from a mixture, is registered with URE.

Sources: Ustawa o odnawialnych źródłach energii — tekst jednolity z 2024 r. (Dz.U. 2024 poz. 1361), art. 2, 7–11a, 23–31; Rozporządzenie MKiŚ z 11 grudnia 2023 r. w sprawie wzoru sprawozdania wytwórcy biogazu lub biometanu (Dz.U. 2023 poz. 2770)

Discussed in the article: Biomethane in Polish law: definition, producer and the URE and KOWR registers

Link to this answer

Must slurry be pasteurised in a biogas plant?

Not always. Category 2 material, such as manure, digestive tract content or milk, can be fed in without prior treatment if the authority sees no serious risk of a transmissible disease. The decision follows from the approval of the establishment.

Sources: Rozporządzenie Komisji (UE) nr 142/2011 — załączniki IV i V (EUR-Lex); Rozporządzenie (WE) nr 1069/2009 (EUR-Lex)

Discussed in the article: Regulation 142/2011 and the biogas plant: pasteurisation at 70°C/60 min, 12 mm and the requirements

Link to this answer

Until when do PMG apply after the 2026 changes?

Generally until 31 December 2030; for biogas up to 300 kW without conversion to biomethane and for biogas plants with interventions under MASE Decree No 99/2024, until 31 December 2037.

Sources: ARERA — uchwała 174/2026/R/eel z 19 maja 2026 r.

Discussed in the article: Italy: Decree-Law 21/2026 changes minimum guaranteed prices for biogas, biomass and bioliquids

Link to this answer

Until when does the green tariff for biogas apply in Ukraine?

According to industry materials from 2020, the tariff is linked to the euro and applies until 1 January 2030, but for biomass and biogas it covers installations commissioned before 1 January 2023.

Sources: Gabinet Ministrów Ukrainy — Rząd podpisał memorandum z producentami zielonej energii; UABIO — pismo w sprawie ograniczenia zielonej taryfy dla biomasy i biogazu; UABIO — materiały o taryfach dla bioenergetyki

Discussed in the article: Ukraine: the green tariff for biogas under Law 810-IX and the 2020 memorandum

Link to this answer

Was a permit always needed to sell digestate in 2022?

As an organic fertiliser, yes, as a rule (Article 3(2) and Article 4). Exceptions concerned, among others, natural fertilisers compliant with Regulation 1069/2009 and fertilisers labelled “EC FERTILISER”, and after 16 July 2022, EU fertilising products.

Sources: Ustawa z dnia 10 lipca 2007 r. o nawozach i nawożeniu — tekst jednolity z 2021 r. (ISAP/ELI); IUNG-PIB — Nawozy organiczne i polepszacze gleby zawierające UPPZ (prezentacja, 2022); Rozporządzenie (UE) 2019/1009 w sprawie produktów nawozowych UE (EUR-Lex)

Discussed in the article: Digestate as a fertiliser: the Minister of Agriculture permit and the requirements of the fertilisers act

Link to this answer

What are minimum guaranteed prices (PMG)?

They top up revenue from the energy market to the level of the plant's operating costs after the support period ends. They do not cover investment costs.

Sources: CIB — komunikat prasowy o uchwale ARERA w sprawie PMG (12.04.2024); ARERA — uchwała 305/2024/R/eel z 23 lipca 2024 r. (aktualizacja PMG)

Discussed in the article: Italy: ARERA introduces minimum guaranteed prices for biogas plants after support ends

Link to this answer

What are RFNBO?

They are renewable fuels of non-biological origin, mainly hydrogen produced from renewable electricity and synthetic fuels made from it. They are not produced from biomass.

Sources: Wniosek COM(2021) 557 — zmiana dyrektywy o OZE (EUR-Lex); Dyrektywa (UE) 2018/2001 (RED II) — EUR-Lex

Discussed in the article: The RED III proposal: a 40% RES target in 2030 and new rules for biogas, hydrogen and biomass

Link to this answer

What capacity is planned for biogas in the Thai FiT 2022–2030?

According to a summary by the law firm Watson Farley & Williams, the annual purchase targets for biogas are five values: 75, 75, 75, 70 and 40 MW (335 MW in total), and the summary does not unambiguously assign them to years.

Sources: Watson Farley & Williams — Thailand's 5 GW renewable PPA FiT scheme 2022–2030; Tilleke & Gibbins — Thailand: regulations on procurement from very small power plants; IEA — Thai Feed-in Tariff (FiT) Policy

Discussed in the article: Thailand: FiT 2022–2030 — biogas from wastewater and waste at 2.0724 baht/kWh

Link to this answer

What does “percentage escalated” mean in the FIT tariff?
What does the abbreviation OIK mean?

It is the Latvian component of the charge for the mandatory purchase (obligātā iepirkuma komponente) of electricity generated in cogeneration and from renewable sources, included in customers'' bills.

Sources: Rada Ministrów Łotwy — Government takes another step towards aligning mandatory procurement component (MPC) (2.09.2020)

Discussed in the article: Latvia: government adopts new rules on mandatory purchase of energy from renewables and cogeneration

Link to this answer

What does the amendment to the Act on Renewable Energy Sources signed on 15 October 2026 change?

The amendment to the Act on Renewable Energy Sources (ustawa o OZE) of 4 September 2026 (Journal of Laws (Dz.U.) 2026, item 1347), signed by the President on 15 October 2026, introduces biomethane auctions (baskets below 2 MW and from 2 MW of electrical capacity), rules for direct gas pipelines for biogas and biomethane, and changes for prosumers and energy storage.

Biomethane auctions will be run by the President of URE; the provisions on them enter into force on 17 February 2027 and apply after a positive decision by the European Commission on state aid. Most of the other provisions apply from 1 December 2026. The Act allows operating support to be combined with investment support within the state aid rules, clarifies biomass and lowers the minimum supply threshold in some biogas and biomass installations. An earlier draft linked biomethane with the provisions on wind turbines and was vetoed in 2025; after the provisions were separated, the wind turbine dispute was removed. Some provisions already entered into force on 17 and 19 October 2026, and some will enter into force after three months (17 January 2027), four (biomethane auctions, 17 February 2027) or twelve months (17 October 2027) from publication (16 October 2026). This is general information.

Sources: gramwzielone.pl: Jest podpis prezydenta pod nowymi przepisami (16.10.2026); enerad.pl: Senat przyjął nowelizację ustawy o OZE; Ustawa o odnawialnych źródłach energii (Dz.U. 2015 poz. 478) — ISAP; Ustawa z 4 września 2026 r. o zmianie ustawy o OZE (Dz.U. 2026 poz. 1347) — API ELI Sejmu

Link to this answer

What does the value before accelerated depreciation mean?
What if an installation has less than 2 MW of thermal capacity?

In that case the Directive does not impose criteria for electricity and heat, but a Member State may extend them. The criteria always apply to biogas or biomethane counted towards transport targets.

Sources: Dyrektywa (UE) 2018/2001 (RED II) — EUR-Lex; Ustawa o odnawialnych źródłach energii z 2015 r. — Internetowy System Aktów Prawnych

Discussed in the article: RED II and biogas plants: sustainability and emission-reduction criteria (Article 29)

Link to this answer

What if emissions from an installation do not require a permit?

If an installation may have a negative impact on the environment and its emissions do not require a permit, it is subject to notification to the environmental protection authority (Article 152 of the Environmental Protection Law, Prawo ochrony środowiska).

Sources: Ustawa z 27 kwietnia 2001 r. – Prawo ochrony środowiska — Internetowy System Aktów Prawnych; Rozporządzenie Ministra Środowiska z 27 sierpnia 2014 r. w sprawie rodzajów instalacji mogących powodować znaczne zanieczyszczenie — Internetowy System Aktów Prawnych; Dyrektywa 2010/75/UE w sprawie emisji przemysłowych — EUR-Lex

Discussed in the article: Environmental permits for biogas plants: emissions, integrated permit and notifications

Link to this answer

What if the operator refuses a grid connection?

A refusal on the grounds of a lack of technical or economic conditions must be justified, and the operator must indicate to the applicant the nearest alternative location if connection there is possible. The President of the Energy Regulatory Office (URE) must also be informed of the refusal.

Sources: Ustawa z 10 kwietnia 1997 r. – Prawo energetyczne — Internetowy System Aktów Prawnych; Rozporządzenie Ministra Gospodarki z 2 lipca 2010 r. w sprawie szczegółowych warunków funkcjonowania systemu gazowego — Internetowy System Aktów Prawnych; Urząd Regulacji Energetyki

Discussed in the article: Connecting a biomethane plant to the gas grid: conditions, costs and liability

Link to this answer

What is a generic tariff (levelised generic tariff)?

It is a rate per kWh averaged over the entire project period, calculated by the regulator on the basis of cost assumptions for a given technology and region. It serves as a reference point for projects subject to regulation.

Sources: Saur Energy — CERC announces levelised generic tariff for RE projects (11.07.2025); Central Electricity Regulatory Commission (CERC) — strona główna; Saur Energy — CERC proposes generic tariffs for hydro and biomass projects for FY23 (17.08.2022)

Discussed in the article: India: CERC generic tariffs for 2025–26 — biogas 10.88 Rs/kWh, biomass 9.43–10.63 Rs/kWh

Link to this answer

What is agricultural biogas under the Act on Renewable Energy Sources?

Agricultural biogas is, in simplified terms, gas from the methane fermentation of agricultural raw materials, agricultural by-products, animal excrement or residues from agri-food processing, excluding biogas from municipal waste and landfills and, as a rule, from sewage treatment plants (the exception concerns on-site sewage treatment plants of agri-food processing).

The definition is found in the Act of 20 February 2015 on Renewable Energy Sources (ustawa o OZE) (Journal of Laws (Dz.U.) 2015, item 478) and has practical significance, because the following depend on it: entry in the KOWR register, access to some support mechanisms and certain simplifications. A biogas plant in the countryside is not automatically "agricultural": what counts is the type of substrates and meeting the conditions of the Act. Biogas from municipal waste, sewage sludge or landfill gas is subject to different regulations. The detailed wording of the provisions has been amended many times, so use the current consolidated text. This is general information.

Sources: Ustawa o odnawialnych źródłach energii (Dz.U. 2015 poz. 478) — ISAP; Krajowy Ośrodek Wsparcia Rolnictwa — gov.pl

Link to this answer

What is eRIN and why does its withdrawal matter for biogas?

eRIN was meant to allow electricity from renewable sources (e.g. from landfill gas) to generate RFS credits when used to power electric vehicles. The EPA concluded that the statute does not permit this, so that revenue channel disappears.

Sources: Beveridge & Diamond — EPA finalizes record-high 2026–2027 RFS volume obligations; EPA — Renewable Fuel Standard (fact sheet Set 2)

Discussed in the article: USA: RFS "Set 2" for 2026–2027 — higher cellulosic volumes, end of eRIN

Link to this answer

What is ETS2 and how does it affect the biomethane market?

ETS2 is a new EU emissions trading system for fuels in buildings and road transport, which is to start from 2028 (after being postponed from 2027), which will raise the cost of fossil fuels and may improve the competitiveness of biomethane.

The decision to postpone ETS2 by a year was taken together with the adoption of the EU climate target for 2040 (a net reduction of 90% relative to 1990), approved by the Council in March 2026. In ETS2 the obligation to surrender allowances rests on fuel suppliers, and the cost is passed on to prices. Biofuels and biomethane that meet the sustainability criteria are in principle treated as zero-emission, so their price relative to fossil fuels falls. The scale of the effect depends on the allowance price, which cannot be predicted with certainty. This is general information.

Sources: electrive.com: Rada UE zatwierdziła cel klimatyczny na 2040 r. (marzec 2026); Dyrektywa 2003/87/WE (EU ETS) — EUR-Lex

Link to this answer

What is RPS in Korea?

It is the Renewable Portfolio Standard: an obligation for large power generators to ensure that a specified percentage of energy comes from renewable sources. They fulfil it by buying or generating REC certificates.

Sources: Argus Media — South Korea raises renewables standard (28.12.2021); Ministerstwo Handlu, Przemysłu i Energii Korei (MOTIE)

Discussed in the article: Korea: RPS obligation rises from 9% to 25% by 2026, and RECs for pellet co-firing are already halved

Link to this answer

What is the maximum value (Höchstwert) in an EEG tender?

It is the upper limit of the price that a participant in a tender for electricity from biomass or biomethane may bid. Bids above the limit are rejected, so the limit sets the maximum bid value (the value to be applied), and not the generator's maximum revenue from selling energy.

Sources: Bundesnetzagentur — Ausschreibungen Biomasse; Solarserver — EEG: Bundesnetzagentur hebt Vergütung für neue Biogasanlagen an (26.02.2024)

Discussed in the article: Germany: Bundesnetzagentur raises price caps in tenders for electricity from biomass and biomethane by 10%

Link to this answer

What is the reference price for biogas in Greece?
What is the reference price of biomethane in Poland?

The regulation of 13 November 2023 set it at PLN 545/MWh for biomethane from agricultural biogas and PLN 538/MWh for biomethane from biogas. The fixed purchase price equals the reference price on the day the declaration is submitted, reduced by investment aid and indexed by the price index.

Sources: Ustawa o odnawialnych źródłach energii — tekst jednolity z 2024 r. (Dz.U. 2024 poz. 1361), rozdział 4a; Rozporządzenie Ministra Klimatu i Środowiska z 13 listopada 2023 r. w sprawie ceny referencyjnej biometanu (Dz.U. 2023 poz. 2477)

Discussed in the article: Support for biomethane in Poland in 2024: what works and what is missing

Link to this answer

What is the register of agricultural biogas producers kept by KOWR?

The register of agricultural biogas producers is kept by the National Support Centre for Agriculture (Krajowy Ośrodek Wsparcia Rolnictwa, KOWR), and an entry is a condition for conducting this activity within the meaning of the Act on Renewable Energy Sources (ustawa o OZE) and for using some of the entitlements and support.

The producer submits an application, and after entry has reporting and updating obligations, for example providing data on the quantity and type of substrates and of the biogas produced. According to KOWR data from May 2026, the register contained 209 installations belonging to 175 entities, and agricultural biogas micro-installations (up to 200,000 m³ of biogas per year), treated as production activity in agriculture, are not fully included in it. An entry does not replace other decisions (environmental, building, waste) and is not a certificate of technological performance. Before submitting an application, check the current forms and requirements on the KOWR website.

Sources: Krajowy Ośrodek Wsparcia Rolnictwa — gov.pl; globenergia.pl: Ile jest w Polsce biogazowni rolniczych w 2026 r.

Link to this answer

What is the tariff for small biogas plants in Italy?
What is the Union Database for Biofuels?

The Union Database for Biofuels (UDB) is an EU database run by the European Commission in which supplies of biofuels and biogas are registered in order to track batches of sustainable fuel and prevent their double counting.

Data on transactions in the supply chain is entered into the database, and certification data is passed to it by voluntary certification schemes; access to the database is available to, among others, economic operators, gas network operators (TSOs/DSOs) and national registers. For biomethane and bioLNG the database is important, because gas in the grid is mixed and origin is tracked through documents. The scope of data and the way biomethane imported from outside the EU is treated have been the subject of discussion and change, which shows that the implementing rules are still developing. If you sell biomethane as a transport fuel, certification data will be linked to the UDB; you will agree the details with the certification body.

Sources: Komisja Europejska: Union Database for Biofuels — materiały szkoleniowe; Dyrektywa (UE) 2023/2413 (RED III) — EUR-Lex

Link to this answer

What must be done after a biogas plant is built in order to start it up?

After construction is completed, the investor reports the facility for acceptance: obtains a permit for use or submits a notification of completion of construction (depending on the category of the facility), and also passes technical supervision acceptance tests and obtains fire safety approvals.

Before start-up, the installation must have a complete set of documents: building acceptance, approval of pressure and gas equipment by the Office of Technical Inspection (Urząd Dozoru Technicznego, UDT), the explosion protection document, operating instructions, entries in registers (e.g. KOWR for agricultural biogas), waste permits and agreements with the grid operator. Only then are trial operation and actual start-up carried out. The lack of any one document may halt start-up. The specific requirements depend on the project; this is general information, not legal advice.

Sources: Ustawa Prawo budowlane — ISAP; Urząd Dozoru Technicznego

Link to this answer

What permits are needed to build a biomethane plant?

A biomethane plant usually requires a set of consents: compliance of the location with the local plan or a decision on development conditions, an environmental decision, a building permit, grid connection conditions, and permits related to waste and emissions.

The exact set depends on the type of substrates, the capacity and the location. When processing waste, a permit for waste processing or an entry in the BDO register is needed, and above the thresholds of the IED Directive also an integrated permit. In addition there are fire and explosion approvals (ATEX), technical supervision acceptance for pressure equipment, and, after construction, a notification or a permit for use. Agricultural biogas activity requires an entry in the register of agricultural biogas producers kept by KOWR, and support for biomethane is linked to certificates from the President of URE. This is general information, not legal advice; the scope of consents is determined individually.

Sources: Ustawa Prawo budowlane — ISAP; Ustawa o udostępnianiu informacji o środowisku (oceny oddziaływania na środowisko) — ISAP; Ustawa Prawo ochrony środowiska — ISAP; Ustawa Prawo energetyczne (Dz.U. 1997 nr 54 poz. 348) — ISAP

Link to this answer

What regulations apply to explosion protection in a biogas plant?

Explosion protection in a biogas plant is governed by two ATEX directives: 1999/92/EC, which obliges the employer to assess the explosion hazard and to provide safe workplaces, and 2014/34/EU, concerning equipment for explosion-hazard zones.

In practice this means preparing an explosion protection document, designating explosion-hazard zones (e.g. around digesters, gas tanks, compressors and upgrading installations), selecting equipment with the appropriate ATEX marking and training employees. In addition, national technical, fire and technical supervision regulations apply. The risk assessment must take into account both biogas (methane, hydrogen sulphide) and the dusts and vapours associated with substrates. Compliance is verified during acceptance tests and inspections.

Sources: Dyrektywa 1999/92/WE (ATEX — ochrona pracowników) — EUR-Lex; Dyrektywa 2014/34/UE (ATEX — urządzenia) — EUR-Lex

Link to this answer

What role do biogas and biomethane have in Polish strategic documents?

Biogas and biomethane are identified in Polish strategic documents on energy and climate as a way of diversifying gas supplies and reducing emissions, although specific targets change with updates of the documents.

The basis is the Energy Policy of Poland until 2040 (Polityka energetyczna Polski do 2040 r., PEP2040) and the National Energy and Climate Plan (Krajowy plan na rzecz energii i klimatu, KPEiK), resulting from the EU regulation on the governance of the energy union. Implementing regulations and support mechanisms, such as the FIP system for biomethane (Articles 83l–83s of the Act on Renewable Energy Sources (ustawa o OZE)) or renewable energy auctions for electricity from biogas, are tools for achieving these goals. The industry points out that the potential is large, but the pace depends on the stability of regulations and on grid access. Current figures and targets should be checked in the documents in force of the Ministry of Climate and Environment.

Sources: Ministerstwo Klimatu i Środowiska; Urząd Regulacji Energetyki

Link to this answer

What targets does the RED III Directive set?

RED III sets for the EU a target of a 42.5% share of renewable energy in gross final energy consumption by 2030 (with an aspiration of 45%) and sectoral sub-targets, including for transport and for advanced biofuels and RFNBO fuels.

In transport, Member States must achieve a renewable energy share of 29% or a 14.5% reduction in greenhouse gas intensity by 2030, with advanced biofuels (Annex IX Part A) and RFNBO together to make up at least 5.5% of energy in transport, with a minimum of 1% from RFNBO. Biomethane from waste and residues, including slurry, can count as an advanced biofuel. The targets apply to the Union as a whole and to Member States, not to individual installations. Implementation details are set by national law. This is general information.

Sources: Dyrektywa (UE) 2023/2413 (RED III) — EUR-Lex; Komisja Europejska — Dyrekcja Generalna ds. Energii

Link to this answer

What was the FIT rate for biogas in Japan?

According to the table in the ERIA study for financial year 2021, the rate for biogas was 39 yen/kWh, and the study indicates that it had been unchanged since the start of the scheme.

Sources: ERIA – Biomass and Wood Pellets: Japan (rozdz. 4)

Discussed in the article: Japan's FIT for biogas: 39 yen per kWh and 20 years of guaranteed purchases

Link to this answer

What was the REFIT 3 tariff for a cogeneration biogas plant?
When does a biogas plant need an integrated permit?

An integrated permit is needed for installations covered by the IED Directive on industrial emissions, and for waste recovery in an anaerobic digestion process the threshold under Annex I to the IED is 100 Mg of waste per day.

The threshold concerns the waste processing capacity of an installation in which the only waste processing is anaerobic digestion; in other arrangements (e.g. with additional composting) a lower threshold of 75 Mg of waste per day applies (point 5.3(b) of Annex I to the IED). An integrated permit covers emissions to air and water, waste management and best available techniques (BAT). Smaller biogas plants usually obtain separate permits, e.g. for emissions to air and a permit for waste processing. The IED was revised in 2024 (Directive 2024/1785), so use the current national provisions. This is general information.

Sources: Dyrektywa 2010/75/UE o emisjach przemysłowych — EUR-Lex; Dyrektywa (UE) 2024/1785 (IED 2.0) — EUR-Lex; Ustawa Prawo ochrony środowiska — ISAP

Discussed in the article: Environmental permits for biogas plants: emissions, integrated permit and notifications

Link to this answer

When will ETS2 actually start operating?

Directive (EU) 2023/959 assumed a start in 2027, but according to the European Commission page updated on 2 September 2026, the system is to be fully operational in 2028. Emissions monitoring started earlier, in 2025.

Sources: Komisja Europejska — ETS2: budynki, transport drogowy i dodatkowe sektory; Dyrektywa (UE) 2023/959 zmieniająca dyrektywę 2003/87/WE — EUR-Lex; Dyrektywa 2003/87/WE (EU ETS) — EUR-Lex

Discussed in the article: ETS2 for buildings and transport: the impact on gas, biomethane and bioCNG

Link to this answer

Which installations does BG16 apply to?

To installations with a capacity below 500 kW that produce electricity mainly from biogas from the digestion of non-hazardous waste and raw plant matter.

Sources: CRE — Délibération n°2023-306 z 5 października 2023 r.

Discussed in the article: France: CRE on changing the indexation of the BG16 tariff for biogas power plants

Link to this answer

Which matters more: the local plan or the environmental decision?

They are two independent stages. The decision on environmental conditions, if required, is issued before the decision on development conditions (WZ) or the building permit, but the location must also comply with the local plan or the WZ decision.

Sources: Ustawa o planowaniu i zagospodarowaniu przestrzennym — Internetowy System Aktów Prawnych; Ustawa z 13 lipca 2023 r. o ułatwieniach w inwestycjach w zakresie biogazowni rolniczych — Dziennik Ustaw

Discussed in the article: Zoning decision or local plan (MPZP)? Siting a biogas plant in spatial planning

Link to this answer

Who can write an environmental impact report?

The author or the head of the team of authors must meet the requirements of Article 74a of the Act on Environmental Impact Assessments (ustawa ooś): relevant fields of study (including natural sciences, chemistry, technical fields related to the environment, agriculture) or higher education and experience in the author teams of reports.

Sources: Ustawa z 3 października 2008 r. o udostępnianiu informacji o środowisku (ustawa ooś) — Internetowy System Aktów Prawnych

Discussed in the article: Environmental impact report for a biogas plant: what it must contain (Article 66 of the Environmental Impact Assessment Act)

Link to this answer

Who do the sustainability criteria of the RED Directive for biomethane apply to?

The sustainability and greenhouse gas emission reduction criteria apply to biomethane that is to be counted towards renewable targets or covered by support, especially in transport, and in heating and electricity for installations above a certain size.

They require, among other things, demonstrating that the feedstock does not come from land of high nature value, and that the fuel achieves a minimum emission reduction compared with the fossil fuel. The required reduction depends on the date of commissioning of the installation and on the use of the gas, and it rises over time: for newer installations it reaches several dozen per cent, even 80%. The RED III Directive changed the installation size thresholds and transitional periods, and EU law provides rules for installations already supported. For these reasons, check the exact requirement for your installation in the text of the directive and with a certification body. This is general information.

Sources: Dyrektywa (UE) 2023/2413 (RED III) — EUR-Lex; Dyrektywa (UE) 2018/2001 (RED II) — EUR-Lex; dena: Biomethane production — legal overview

Link to this answer

Who imposes penalties on a biogas plant?

It depends on the infringement. For waste, emissions and use of the environment, the voivodeship environmental protection inspector imposes the penalty; for the register of agricultural biogas producers, the Director General of KOWR; for infringements in the area of energy and licences, the President of the Energy Regulatory Office (URE).

Sources: Ustawa z 14 grudnia 2012 r. o odpadach (rozdz. 2 – administracyjne kary pieniężne) — Internetowy System Aktów Prawnych; Ustawa z 20 lutego 2015 r. o odnawialnych źródłach energii (art. 168–176) — Internetowy System Aktów Prawnych; Krajowy Ośrodek Wsparcia Rolnictwa

Discussed in the article: Liability and penalties: what a biogas plant risks for breaching regulations

Link to this answer

Who inspects a biogas plant?

A biogas plant may be inspected by various authorities depending on the scope: the environmental protection inspectorate, building supervision, the Office of Technical Inspection (UDT), the labour inspectorate, the veterinary inspectorate, the fire brigade, and KOWR and URE within their areas of competence.

The environmental protection inspectorate checks emissions, waste management and the use of digestate. UDT supervises pressure and gas equipment, and the labour inspectorate occupational health and safety. The veterinary inspectorate inspects the processing of animal by-products, and KOWR the agricultural biogas register. The fire brigade checks fire protection. The President of URE issues, among other things, certificates (e.g. concerning support for biomethane) and checks the accuracy of information and declarations submitted in connection with support. A common rule: documentation must be complete and available on site, because inspections often cover the conformity of declared substrates with the actual ones.

Sources: Główny Inspektorat Ochrony Środowiska — gov.pl; Urząd Dozoru Technicznego; Państwowa Inspekcja Pracy; Główny Inspektorat Weterynarii — gov.pl

Link to this answer

Who issues guarantees of origin for biomethane in Poland?

The guarantee is issued by the President of the Energy Regulatory Office (URE) on the basis of the producer's application, which is first verified by the gas grid operator (or an accredited body in the case of transport outside the grid). The register of guarantees is kept by the entity operating a commodity exchange or a regulated market.

Sources: Ustawa o odnawialnych źródłach energii — tekst jednolity z 2024 r. (Dz.U. 2024 poz. 1361), art. 120–125; Rozporządzenie MKiŚ z 26 czerwca 2024 r. w sprawie pomiarów, rejestracji i obliczania ilości biogazu, biogazu rolniczego i biometanu (Dz.U. 2024 poz. 974); Dyrektywa (UE) 2018/2001 (RED II), art. 19 — EUR-Lex

Discussed in the article: Guarantees of origin for biogas and biomethane: who issues them, how to apply and how to redeem them

Link to this answer

Who issues waste management licences in Egypt?
Who tests biomethane quality?

Testing at the entry point is carried out by the biomethane producer on its own equipment, while the gas system operator checks quality in the grid and may refuse to accept gas that does not meet the parameters. Supervision is exercised by the President of the Energy Regulatory Office (URE).

Sources: Rozporządzenie Ministra Gospodarki z 2 lipca 2010 r. w sprawie szczegółowych warunków funkcjonowania systemu gazowego — Internetowy System Aktów Prawnych; Urząd Regulacji Energetyki; Ustawa z 20 lutego 2015 r. o odnawialnych źródłach energii (art. 118) — Internetowy System Aktów Prawnych

Discussed in the article: Biomethane quality in the gas grid: the parameters in the regulation and who checks them

Link to this answer

Will a biogas plant have to move to a two-way CfD?

Not under Article 19d: the list of technologies covers wind, solar, geothermal, run-of-river hydro and nuclear energy. However, Member States may also apply CfDs to other technologies. The Irish RESS scheme is an example of a voluntary two-way CfD, applied even before the Article 19d deadline.

Sources: Rozporządzenie (UE) 2024/1747 — EUR-Lex; Komisja Europejska — Electricity market design

Discussed in the article: Electricity market reform 2024/1747: two-way CfDs from 2027 — will they cover biogas and biomass?

Link to this answer

Would a Swedish biogas plant get elcertificates today?

Only if the installation was commissioned before the end of 2021 and 15 years have not passed since it was commissioned. New installations after 31 December 2021 can no longer receive certificates.

Sources: Energimyndigheten — The electricity certificate system; Clean Energy for EU Islands — Szwecja: quota system; Rząd Szwecji — proposition 2020/21:16 (zakończenie systemu elcertyfikatów)

Discussed in the article: Sweden: electricity certificates and energy from biogas — new installations until the end of 2021, system until 2035

Link to this answer